Fca Permission for Diversion of Protected Forest Land 0.0224 Ha by Laying 11 KV 2-Nos Power Transmission Line Underground

Fca Permission for Diversion of Protected Forest Land 0.0224 Ha by Laying 11 KV 2-Nos Power Transmission Line Underground is an approved power project in Untdi, Valsad, Gujarat. The site covers 0 acres. Its stated project cost is ₹9 lakh. As of 27 Nov 2026, its status is “Forest land use approved” (since 8 Dec 2025).

See it on the live map All projects in Valsad

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Fca Permission for Diversion of Protected Forest Land 0.0224 Ha by Laying 11 KV 2-Nos Power Transmission Line Underground is an approved power project in Untdi, Valsad, Gujarat. The site covers 0 acres.

Who is building it?

The applicant is Kpi Green Energy Limited.

Has it been approved?

Yes. Its status is “Forest land use approved” (since 8 Dec 2025), as of 27 Nov 2026.

Where is it?

In Untdi, Valsad, Gujarat.

How big is it?

It has a stated cost of ₹9 lakh; a site of 0 acres and 220 m² of forest land.

When was it filed?

The application was filed on 17 Oct 2025.

Project details

Official titleFca Permission for Diversion of Protected Forest Land 0.0224 Ha by Laying 11 KV 2-Nos Power Transmission Line Underground at Untadi Village, District Valsad
StatusForest land use approved
Status since8 Dec 2025
Application filed17 Oct 2025
Approval soughtForest land use
Application typeNew project
SectorPower
ApplicantKpi Green Energy Limited
Land area200 m²
Forest land220 m²
Project cost₹9 lakh
Village / localityUntdi
Taluk / tehsilValsad
DistrictValsad
StateGujarat
Location fromSite boundary on record
Our referenceWID-GJ-14110

In context

16 applications in Valsad since January 2022 are in the same category (Power): 9 approved, 3 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 13 months from filing to approval. At 0 acres, this one is smaller than 92% of them.

1 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Untdi, Valsad, Gujarat. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 37 Kpi Green Energy projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.