| Official title | Diversion of 27.5371 Forest Land for the Vulnerable Identified Sites for the Dredging Works in River Beas. Falling in District Kullu H.P. |
|---|---|
| Status | More information requested |
| Status since | 12 Nov 2026 |
| Application filed | 13 Jul 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Mining |
| Applicant | HIMACHAL PRADESH STaTE FOREST DEVELOPMENT CORPORATION LIMITED |
| Land area | 68.1 acres (27.5 ha) |
| Forest land | 68 acres (27.5 ha) |
| Project cost | ₹12 crore |
| Village / locality | Up Muhal Barnar |
| Taluk / tehsil | Manali |
| District | Kullu |
| State | Himachal Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-HP-01660 |
In context
32 applications in Kullu since January 2022 are in the same category (Mining): 15 approved, 9 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 68.1 acres, this one is larger than 97% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Up Muhal Barnar, Manali, Kullu, Himachal Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Day Boarding School At Jagatsukh Tehsil Manali — lapsed, 2.9 km away
- Construction of Heliport near Green Tax Barrier Manali — forest land use approved, 3 km away
- Dredging in river Beas from Garbage Treatment plant to Bahanu Bridge… — under forest review, 3.8 km away
- Pakhnoj-II SHEP (5.0 MW) — under forest review, 4.2 km away
- Gau Sadan at Rangri — lapsed, 4.4 km away
- Construction of Road Khasra No. 2262/1328/1 to Khasra No. 2171/1341 — under forest review, 4.5 km away
- Chhaki Nala SHEP (2.5 MW) — not approved, 7 km away
- Chhaki Nala Small HEP (2.5 MW) — lapsed, 7 km away
More from HIMACHAL PRADESH STaTE FOREST DEVELOPMENT CORPORATION LIMITED in Kullu
- DIVERSION OF 3.54 HECTARE FOREST LAND(Shirar-2) FOR THE VULNERABLE SITES FOR… — lapsed
- Diversion of 6.7207 Hectare Forest Land for the Vulnerable Sites for the… — under forest review
- River Bed Dredging From nehru kund bridge to bahng in River Beas — under forest review
- Dredging in river Beas from Garbage Treatment plant to Bahanu Bridge… — under forest review
- Diversion of 8.8725 Ha Forest Land for the Sites I.E. Dohlunala and Raison for… — more information requested
- Extraction of sand, stone and bajri from Tukra No. 1, measuring 04-38-00… — environmental approval granted
10 HIMACHAL PRADESH STaTE FOREST DEVELOPMENT CORPORATION projects in Kullu
All 11 HIMACHAL PRADESH STaTE FOREST DEVELOPMENT CORPORATION projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.