Quick answers
What is this project?
Proposed Integrated Manufacturing facility of Auto Components is a proposed building project in Tatarpur(47), Palwal, Haryana. The site covers 9.7 acres.
Who is building it?
The applicant is Sai Auto Components Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Tatarpur(47), Palwal, Haryana.
How big is it?
It has a stated cost of ₹100 crore and a site of 9.7 acres.
When was it filed?
The application was filed on 1 Oct 2026.
Project details
| Status | Under environmental review |
|---|---|
| Status since | 27 Nov 2026 |
| Application filed | 1 Oct 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Sai Auto Components Private Limited |
| Land area | 9.7 acres (3.9 ha) |
| Project cost | ₹100 crore |
| Village / locality | Tatarpur(47) |
| Taluk / tehsil | Palwal |
| District | Palwal |
| State | Haryana |
| Location from | Site boundary on record |
| Our reference | WID-HR-01130 |
In context
30 applications in Palwal since January 2022 are in the same category (Buildings & townships): 9 approved, 11 filed or under review, and 10 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 9.7 acres, this one is larger than 67% of them.
12 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Tatarpur(47), Palwal, Haryana. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Jyoti Strips Private Limited "Proposed Cold Rolling Mill Complex with… — under environmental review, 600 m away
- Jyoti Strips Private Limited "Proposed Cold Rolling Mill Complex with… — environmental approval granted, 600 m away
- Jyoti Strips Private Limited "Proposed Cold Rolling Mill Complex with… — cleared for impact study, 600 m away
- Proposed Cement Grinding Unit with Cement Production Capacity of 2 x 3 Million… — environmental approval granted, 750 m away
- Proposed Cement Grinding Unit with Cement Production Capacity of 2 x 3 Million… — cleared for impact study, 750 m away
- ENVIRONMENTAL CLEARANCE FOR SETTING UP OF INDUSTRIAL UNIT (FERROUS AND NON-… — under environmental review, 950 m away
- Diversion of 0.2038 Ha. of Forest Land for laying of PNG Pipeline on Village -… — lapsed, 1.4 km away
- Proposed expansion of existing Industrial Unit by M/s Knorr Bremse India… — environmental approval granted, 2.7 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.