Quick answers
What is Piparwar UG (Phase-I)?
Piparwar UG (Phase-I) is an approved mining project in Kutki Khurd Alias Thena, Tandwa, Chatra, Jharkhand. The site covers 1,148.3 acres.
Who is building it?
The applicant is Central Coalfields Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 29 Oct 2024), as of 27 Nov 2026.
Where is it?
In Kutki Khurd Alias Thena, Tandwa, Chatra, Jharkhand.
How big is it?
It has a stated cost of ₹392.8 crore and a site of 1,148.3 acres.
When was it filed?
The application was filed on 19 Sept 2024.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 19 Sept 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Central Coalfields Limited |
| Land area | 1,148.3 acres (464.7 ha) |
| Project cost | ₹392.8 crore |
| Village / locality | Kutki Khurd Alias Thena |
| Taluk / tehsil | Tandwa |
| District | Chatra |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-01021 |
In context
47 applications in Chatra since January 2022 are in the same category (Mining): 34 approved, 7 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1,148.3 acres, this one is larger than 64% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 1,178.9 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 5 mining leases have applied within 5 km.
Where it is
Kutki Khurd Alias Thena, Tandwa, Chatra, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendment in EC of Piparwar UG (Phase-I) — environmental approval granted, 0 m away
- Piparwar UG (Phase-I) — withdrawn, 0 m away
- Piparwar UG (Phase-I) — cleared for impact study, 0 m away
- Piparwar OCP Change in land Use 28.22 Ha — lapsed, 400 m away
- Piparwar OCP Change in land Use 101.87 Ha — lapsed, 750 m away
- Piparwar OCP Change in land Use 13.11 Ha — lapsed, 1.6 km away
- Ashok OCP 10 MTY — lapsed, 1.9 km away
- Prepration of 11KV Line for Supply of Electricity for Phed(Wtp) From Tandwa… — lapsed, 2.7 km away
More from Central Coalfields Limited in Chatra
- Amrapali Opencast Coal Mining Project — under environmental review
- Sanghamitra Opencast Project (Project Area: 2254.02 Ha, Capacity: 20.0 MTY) — cleared for impact study
- Ashok OCP 10 MTY — lapsed
- Sanghamitra OCP — more information requested
- Magadh OCP (Increase in production capacity from 20 MTPA to 24 MTPA, Project… — environmental approval granted
- Ashok Expansion OCP — lapsed
20 Central Coalfields projects in Chatra
All 66 Central Coalfields projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.