What is Piparwar OCP Change in land Use 13.11 Ha?
Piparwar OCP Change in land Use 13.11 Ha is a lapsed mining project in Piparwar Alias Mangardahal, Tandwa, Chatra, Jharkhand. The site covers 7 acres.
Who is building it?
The applicant is Central Coalfields Limited.
Has it been approved?
No. The application was lapsed on 24 Nov 2026, so it is no longer under consideration.
Where is it?
In Piparwar Alias Mangardahal, Tandwa, Chatra, Jharkhand.
How big is it?
It has a site of 7 acres and 7 acres (2.8 ha) of forest land.
When was it filed?
The application was filed on 21 Sept 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 24 Nov 2026 |
| Application filed | 21 Sept 2023 |
| Approval sought | Forest land use |
| Application type | Change of use |
| Sector | Mining |
| Applicant | Central Coalfields Limited |
| Land area | 7 acres (2.8 ha) |
| Forest land | 7 acres (2.8 ha) |
| Village / locality | Piparwar Alias Mangardahal |
| Taluk / tehsil | Tandwa |
| District | Chatra |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02236 |
In context
47 applications in Chatra since January 2022 are in the same category (Mining): 34 approved, 7 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 7 acres, this one is smaller than 51% of them.
No other mining lease on record is within 500 m of this site; 5 have applied within 5 km.
Where it is
Piparwar Alias Mangardahal, Tandwa, Chatra, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendment in EC of Piparwar UG (Phase-I) — environmental approval granted, 1.6 km away
- Piparwar UG (Phase-I) — withdrawn, 1.6 km away
- Piparwar UG (Phase-I) — environmental approval granted, 1.6 km away
- Piparwar UG (Phase-I) — cleared for impact study, 1.6 km away
- Piparwar OCP Change in land Use 28.22 Ha — lapsed, 2 km away
- Piparwar OCP Change in land Use 101.87 Ha — lapsed, 2.4 km away
- Prepration of 11KV Line for Supply of Electricity for Phed(Wtp) From Tandwa… — lapsed, 2.7 km away
- Ashok OCP 10 MTY — lapsed, 3.2 km away
More from Central Coalfields Limited in Chatra
- Amrapali Opencast Coal Mining Project — under environmental review
- Sanghamitra Opencast Project (Project Area: 2254.02 Ha, Capacity: 20.0 MTY) — cleared for impact study
- Ashok OCP 10 MTY — lapsed
- Sanghamitra OCP — more information requested
- Magadh OCP (Increase in production capacity from 20 MTPA to 24 MTPA, Project… — environmental approval granted
- Ashok Expansion OCP — lapsed
20 Central Coalfields projects in Chatra
All 66 Central Coalfields projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.