Quick answers
What is Integrated Steel Plant (2.5 MTPA)?
Integrated Steel Plant (2.5 MTPA) is an approved industrial project in Mahali Murup, Saraikela, Saraikela-Kharsawan, Jharkhand. The site covers 184.4 acres.
Who is building it?
The applicant is Rungta Sons Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 21 Dec 2025), as of 27 Nov 2026.
Where is it?
In Mahali Murup, Saraikela, Saraikela-Kharsawan, Jharkhand.
How big is it?
It has a stated cost of ₹750 crore and a site of 184.4 acres.
When was it filed?
The application was filed on 10 Nov 2025.
Project details
| Official title | Integrated Steel Plant (2.5 MTPA) along with Captive Power Plant (280 MW; WHRB 140 MW & AFBC 140 MW) |
|---|---|
| Status | Environmental approval granted |
| Status since | 21 Dec 2025 |
| Application filed | 10 Nov 2025 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Industry |
| Applicant | Rungta Sons Private Limited |
| Land area | 184.4 acres (74.6 ha) |
| Project cost | ₹750 crore |
| Village / locality | Mahali Murup |
| Taluk / tehsil | Saraikela |
| District | Saraikela-Kharsawan |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-01370 |
In context
47 applications in Saraikela-Kharsawan since January 2022 are in the same category (Industry): 24 approved, 11 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 184.4 acres, this one is larger than 81% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Mahali Murup, Saraikela, Saraikela-Kharsawan, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of 0.35 MTPA DRI & 60 MW CPP in 37.313 ha into "Seraikela-Kharsawan… — cleared for impact study, 250 m away
- Expansion of Standalone Clinker Grinding Unit for manufacturing of Cement… — environmental approval granted, 3 km away
- Chhota Tangrani Stone Deposit, Mauza- Chhota Tangrani, P.S.- Saraikela, Thana… — environmental approval granted, 6.6 km away
- Chota Tangrani Stone Mine — environmental approval granted, 6.7 km away
- Expansion of Srijan Steel and Power Industries Private Limited by Production… — lapsed, 7.2 km away
- Expansion of Srijan Steel and Power Industries Private Limited by Production… — cleared for impact study, 7.2 km away
- Proposed Integrated Steel Plant with Sponge Iron (DRI) 2,31,000 TPA, Steel… — environmental approval granted, 7.2 km away
- Proposed Integrated Steel Plant with Sponge Iron (DRI) 2,31,000 TPA, Steel… — cleared for impact study, 7.2 km away
More from Rungta Sons Private Limited in Saraikela-Kharsawan
- Expansion of 0.35 MTPA DRI & 60 MW CPP in 37.313 ha into "Seraikela-Kharsawan… — cleared for impact study
All 40 Rungta Sons projects across India