Cleared for impact studyIndustry · Giridih, Jharkhand

Expansion in existing Rolling Mill to increase production from 250000TPA to 482320TPA by adding 40TPH RHF to existing 36TPH RHF with addition of 2x400TPD DRI Kiln to produce Sponge Iron of 264000TPA, IF of 4x25tonnes with CCM of 6x11m radius to produce MS Billets of 330000TPA, MS Pipes/Tubes of 300000TPA & Fe-Alloy plant with 4x9MVA SAF to produce 135400TPA Si-Mn/73400 TPA Fe-Si/169000TPA Fe-Mn/134000Fe-Cr, 25Ton AOD for Low C Fe-alloys, CPP 36MW (WHRB#20MW & CFBC#16MW) & Briquetting Unit 10TPH

Expansion in existing Rolling Mill to increase production from 250000TPA to 482320TPA by adding 40TPH RHF to existing 36TPH RHF with addition of 2x400TPD DRI Kiln to produce Sponge Iron of 264000TPA, IF of 4x25tonnes with CCM of 6x11m radius to produce MS Billets of 330000TPA, MS Pipes/Tubes of 300000TPA & Fe-Alloy plant with 4x9MVA SAF to produce 135400TPA Si-Mn/73400 TPA Fe-Si/169000TPA Fe-Mn/134000Fe-Cr, 25Ton AOD for Low C Fe-alloys, CPP 36MW (WHRB#20MW & CFBC#16MW) & Briquetting Unit 10TPH is a proposed industrial project in Bhorandi, Giridih, Jharkhand. The site covers 41.1 acres. Its stated project cost is ₹880.6 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 2 Sept 2025).

See it on the live map All projects in Giridih

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

StatusCleared for impact study
Status since2 Sept 2025
Application filed21 Aug 2025
Approval soughtEnvironmental approval
Application typeEarly planning
SectorIndustry
ApplicantRebanta Steels Private Limited
Land area41.1 acres (16.7 ha)
Project cost₹880.6 crore
Village / localityBhorandi
Taluk / tehsilGiridih
DistrictGiridih
StateJharkhand
Location fromSite boundary on record
Our referenceWID-JH-01640

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 21 Aug 2026More information requested41.1 acres₹880.6 crore
Early planning filed 21 Aug 2025 (this page)Cleared for impact study41.1 acres₹880.6 crore

In context

29 applications in Giridih since January 2022 are in the same category (Industry): 20 approved, 4 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 39 days from filing to approval. At 41.1 acres, this one is larger than 76% of them.

29 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Bhorandi, Giridih, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Rebanta Steels Private Limited in Giridih

All 4 Rebanta Steels projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.