29industry projects
4filed or under review
0filed in the last 30 days

Where they are in the approval process

StatusProjects
Filed or under review4
Approved20
Withdrawn or lapsed5

Recently approved

ProjectTypeSizeStatusFiled
Greenfield Plant for Production of 123,000 TPA (max.) Ferro Alloy or 154,000 TPA Pig…
Majhiladh, Giridih
Industry82.6 acresEnvironmental approval granted14 May 2026
Expansion in existing Rolling Mill to increase production from 250000TPA to 482320TPA by…
Bhorandi, Giridih
Industry41.1 acresCleared for impact study21 Aug 2025
Environmental Clearance for Enhancing the Production of Tmt Bars/Rods From 16,500tpa to…
Mahtodih, Giridih
Industry18.7 acresEnvironmental approval granted15 May 2025
Environmental Clearance for Enhancing the Production of Tmt Bars/Rods From 16,500tpa to…
Mahtodih, Giridih
Industry18.7 acresEnvironmental approval granted12 Mar 2025
Enhancement of Sponge Iron Production from 90,000 TPA to 99,000 TPA (by increasing…
Majhiladh, Giridih
Industry8.8 acresEnvironmental approval granted6 Jan 2025
Greenfield Plant for Production of 123,000 TPA (max.) Ferro Alloy or 154,000 TPA Pig…
Majhiladh, Giridih
Industry82.6 acresCleared for impact study17 Jan 2025
Environmental Clearance for Expansion of Sponge Iron Plant from 33,000 TPA to 62,700 TPA…
Mahuatanr, Giridih
Industry27.5 acresEnvironmental approval granted12 Dec 2024
Expansion of Sponge iron plant production from 33,000TPA to 62700 TPA by enhancement of…
Gadi, Giridih
Industry40 acresEnvironmental approval granted14 Dec 2024
Expansion of Sponge Iron Plant of M/s Atibir Industries Co. Ltd. by addition of 15 MVA…
Majhiladh, Giridih
Industry27.7 acresEnvironmental approval granted22 Oct 2024
Expansion & Modernization for Enhancing the Production of 60,000 Tpa Ingots to 1,48,500…
Mohanpur, Giridih
Industry10.4 acresEnvironmental approval granted20 Aug 2024

Recently filed

ProjectTypeSizeStatusFiled
Greenfield Steel Plant for production of 1,50,000 TPA Pig iron, 1,05,000 TPA Sponge…
Majhiladh, Giridih
Industry49.3 acresUnder environmental review1 Oct 2026
Expansion in existing Rolling Mill to increase production from 250000TPA to 482320TPA by…
Bhorandi, Giridih
Industry41.1 acresMore information requested21 Aug 2026
Expansion of existing Sponge Iron Plant from 33,000TPA to 264,000TPA through existing…
Chatro, Giridih
Industry34.6 acresUnder environmental review26 Jun 2026
Expansion of Ingot/Billet Production from 16,800 TPA to 6,99,600 TPA (Installation of…
Harsingh Raidih, Giridih
Industry18.5 acresUnder environmental review6 Jun 2026
Greenfield Plant for Production of 123,000 TPA (max.) Ferro Alloy or 154,000 TPA Pig…
Majhiladh, Giridih
Industry82.6 acresEnvironmental approval granted14 May 2026
Proposed Expansion of Rolling Mill (from 90,000 TPA to 1,15,200 TPA for Production of…
Turukdiha, Giridih
Industry13.5 acresLapsed1 May 2026
Greenfield Ferro Alloy plant with 3 x 9 MVA SAF to produce 50,100 TPA of Si-Mn (or)…
Jambad, Giridih
Industry22.6 acresLapsed19 Feb 2026
Expansion in existing Rolling Mill to increase production from 250000TPA to 482320TPA by…
Bhorandi, Giridih
Industry41.1 acresCleared for impact study21 Aug 2025
Environmental Clearance for Enhancing the Production of Tmt Bars/Rods From 16,500tpa to…
Mahtodih, Giridih
Industry18.7 acresEnvironmental approval granted15 May 2025
Environmental Clearance for Enhancing the Production of Tmt Bars/Rods From 16,500tpa to…
Mahtodih, Giridih
Industry18.7 acresEnvironmental approval granted12 Mar 2025
Greenfield Plant for Production of 123,000 TPA (max.) Ferro Alloy or 154,000 TPA Pig…
Majhiladh, Giridih
Industry82.6 acresCleared for impact study17 Jan 2025
Enhancement of Sponge Iron Production from 90,000 TPA to 99,000 TPA (by increasing…
Majhiladh, Giridih
Industry8.8 acresEnvironmental approval granted6 Jan 2025
Expansion of Sponge iron plant production from 33,000TPA to 62700 TPA by enhancement of…
Gadi, Giridih
Industry40 acresEnvironmental approval granted14 Dec 2024
Environmental Clearance for Expansion of Sponge Iron Plant from 33,000 TPA to 62,700 TPA…
Mahuatanr, Giridih
Industry27.5 acresEnvironmental approval granted12 Dec 2024
Expansion of Sponge Iron Plant of M/s Atibir Industries Co. Ltd. by addition of 15 MVA…
Majhiladh, Giridih
Industry27.7 acresEnvironmental approval granted22 Oct 2024
Expansion & Modernization for Enhancing the Production of 60,000 Tpa Ingots to 1,48,500…
Mohanpur, Giridih
Industry10.4 acresEnvironmental approval granted20 Aug 2024
Environmental Clearance for Expansion of Sponge Iron Plant from 33,000 TPA to 62,700 TPA…
Majhiladh, Giridih
Industry27.5 acresCleared for impact study27 May 2024
Expansion of Sponge iron plant production from 33,000TPA to 62700 TPA by enhancement of…
Gadi, Giridih
Industry40 acresCleared for impact study15 May 2024
Environmental Clearance for Enhancing the Production of Tmt Bars From 27000 Tpa to…
Ajidih, Giridih
Industry2.8 acresEnvironmental approval granted24 Apr 2024
Expansion of existing Rolling Mill from Production Capacity of TMT Bars - 28,800 TPA to…
Bhorandiha, Giridih
Industry17.1 acresEnvironmental approval granted23 Apr 2024
Expansion of existing Sponge Iron Plant from 33,000TPA to 264,000TPA through existing…
Chatro, Giridih
Industry34.6 acresCleared for impact study23 Apr 2024
Environmental Clearance for Production of M.S Angle, Channel, Flats & Squares, Capacity-…
Biswasdih, Giridih
Industry2.4 acresLapsed17 Jan 2024
Steel Plant with facilities of SMS unit for producing 56100TPA MS Billets with 2x12T IF…
Harsingh Raidih, Giridih
Industry42.1 acresLapsed3 Oct 2023
Steel Plant with facilities of SMS unit for producing 56100TPA MS Billets with 2x12T IF…
Harsingh Raidih, Giridih
Industry42.1 acresWithdrawn18 Sept 2023
Environmental Clearance for Enhancing the Production of Tmt Bars/Rods From 16,500tpa to…
Mahtodih, Giridih
Industry18.7 acresEnvironmental approval granted15 Aug 2023
Expansion of existing Rolling Mill form Production Capacity of TMT Bars – 29,000 TPA to…
Majhiladh, Giridih
Industry13.9 acresCleared for impact study15 Jul 2023
Expansion of existing Rolling Mill from Production Capacity of TMT Bars - 28,800 TPA to…
Bhorandiha, Giridih
Industry17.1 acresCleared for impact study12 Apr 2023
Environmental Clearance for Enhancing the Production of Tmt Bars From 27000 Tpa to…
Ajidih, Giridih
Industry2.8 acresCleared for impact study12 Apr 2023
Environmental Clearance for Enhancing the Production of Tmt Bars/Rods From 16,500tpa to…
Mahtodih, Giridih
Industry18.7 acresCleared for impact study15 Nov 2022

Questions people ask

How many industry projects are planned in Giridih?

29 industry projects in Giridih have applied for approval since January 2022. 24 of them are active (not withdrawn, lapsed or rejected) and 4 are still awaiting a decision.

What was approved most recently in Giridih?

Greenfield Plant for Production of 123,000 TPA (max.) Ferro Alloy or 154,000 TPA Pig Iron or 31,000 TPA Metallurgical Grade Silicon Metal, Captive Power Plant of 6MW (WHRB-2x1 MW + 2x2MW), 20 TPH Jigging Plant and Fly Ash Brick Manufacturing unit of 240,000 TPA by M/s CR Advanced Materials Pvt. Ltd in Majhiladh — “Environmental approval granted” on 13 Aug 2026.

How often is this list updated?

Twice a day. The data on this page was last refreshed on 27 Nov 2026, 6:36 am IST.