What is this project?
Expansion of the existing steel plant for final production of 315,000 TPA Sponge Iron, 435,600 TPA MS Billets through IF, LRF and CCM, 40 MW CPP is a proposed industrial project in Kamta, Gola, Ramgarh, Jharkhand. The site covers 75.1 acres.
Who is building it?
The applicant is Brahmaputra Metallics Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 19 Mar 2026), as of 27 Nov 2026.
Where is it?
In Kamta, Gola, Ramgarh, Jharkhand.
How big is it?
It has a stated cost of ₹1,078.9 crore and a site of 75.1 acres.
When was it filed?
The application was filed on 10 Mar 2026.
Project details
| Official title | Expansion of the existing steel plant for final production of 315,000 TPA Sponge Iron, 435,600 TPA MS Billets through IF, LRF and CCM, 40 MW CPP along with installation of 450,000 TPA Pig Iron Plant, 383,200 TPA Sinter Plant, 350,000 TPA SS Billets through EAF, LRF & CCM, 28,500 TPA (max) Ferro Alloys, 300,000 TPA Rolling Mill and 12,00,000 TPA Pellet Plant along with allied facilities by Brahmaputra Metallics Limited at Village Kamta, Dist Ramgarh, Jharkhand |
|---|---|
| Status | Cleared for impact study |
| Status since | 19 Mar 2026 |
| Application filed | 10 Mar 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Brahmaputra Metallics Limited |
| Land area | 75.1 acres (30.4 ha) |
| Project cost | ₹1,078.9 crore |
| Village / locality | Kamta |
| Taluk / tehsil | Gola |
| District | Ramgarh |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-01958 |
In context
30 applications in Ramgarh since January 2022 are in the same category (Industry): 12 approved, 10 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 31 days from filing to approval. At 75.1 acres, this one is larger than 73% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kamta, Gola, Ramgarh, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of the existing 28692 TPA MS Billets plant for final production of… — under environmental review, 3.7 km away
- Expansion of the existing steel plant for final production of 1,98,000 TPA MS… — withdrawn, 3.7 km away
- Change in Land Use of Rajrappa Ocp — lapsed, 7.9 km away
- Rola Stone Deposit (Area - 2.812 ha) — environmental approval granted, 8.1 km away
- Change in Land Use of Rajrappa Ocp — lapsed, 8.2 km away
- Widening / Strengthening and Reconstruction of Four Lane of Gola to Muri Road… — lapsed, 8.3 km away
- 132 KV D/C Gola Silli Transmission Line — under forest review, 8.8 km away