Transfer of Environment Clearance "Expansion of Integrated Steel Plant Project is a lapsed industrial project in Tirildih, Chandil, Saraikela-Kharsawan, Jharkhand. The site covers 48.8 acres.
Who is building it?
The applicant is Orissa Alloy Steel PVT. LTD..
Has it been approved?
No. The application was lapsed on 17 Jun 2026, so it is no longer under consideration.
Where is it?
In Tirildih, Chandil, Saraikela-Kharsawan, Jharkhand.
How big is it?
It has a stated cost of ₹286.4 crore and a site of 48.8 acres.
When was it filed?
The application was filed on 18 Feb 2026.
Project details
| Official title | Transfer of Environment Clearance "Expansion of Integrated Steel Plant Project along with Captive Power Plant (7 MW) and Coal Washery (40 TPH Jig) located at Village Tiruldih & Palgam, Kaushalgarh, Chowka-Kandra Road, P.O. Ghatdulmi, Tehsil Chandil, District Saraikela Kharsawan, Jharkhand" from Divine Alloys & Power Co. Limited to Orissa Alloy Steel Private Limited |
|---|---|
| Status | Lapsed |
| Status since | 17 Jun 2026 |
| Application filed | 18 Feb 2026 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Industry |
| Applicant | Orissa Alloy Steel PVT. LTD. |
| Land area | 48.8 acres (19.7 ha) |
| Project cost | ₹286.4 crore |
| Village / locality | Tirildih |
| Taluk / tehsil | Chandil |
| District | Saraikela-Kharsawan |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02066 |
In context
47 applications in Saraikela-Kharsawan since January 2022 are in the same category (Industry): 24 approved, 11 filed or under review, and 12 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 48.8 acres, this one is larger than 55% of them.
8 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Tirildih, Chandil, Saraikela-Kharsawan, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of the Existing Project Land From 2.6365 Ha to 6.7177 Ha for… — lapsed, 750 m away
- Expansion of the Existing Project Land From 2.6365 Ha to 6.7177 Ha for… — cleared for impact study, 750 m away
- "Expansion at existing site by new installation of Ferro alloy (Si-Mn) 30,000… — withdrawn, 750 m away
- Expansion of existing steel plant by enhancement of Pig iron production from… — environmental approval granted, 3.3 km away
- Expansion of existing steel plant by enhancement of Pig iron production from… — cleared for impact study, 3.3 km away
- Proposed Integrated steel plant with Captive Power Plant (50 MW) by Narsingh… — environmental approval granted, 3.3 km away
- Rudia Stone Mine — environmental approval granted, 4.8 km away
- 220 Kv D/C Chandil to Chandil Transmission Line — initial checks, 4.8 km away
All 12 Orissa Alloy Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.