What is this project?
Dugda Coking Coal Washery of 6.0 MTPA capacity by M/s JSW Steel Limited is a proposed mining project in Bursera, Chandrapura, Bokaro, Jharkhand. The site covers 70.7 acres.
Who is building it?
The applicant is Jsw Steel LTD.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Bursera, Chandrapura, Bokaro, Jharkhand.
How big is it?
It has a stated cost of ₹301 crore and a site of 70.7 acres.
When was it filed?
The application was filed on 13 Mar 2026.
Project details
| Official title | Dugda Coking Coal Washery of 6.0 MTPA capacity at Village - Bursera, Tehsil - Dugda, District - Bokaro, Jharkhand by M/s JSW Steel Limited |
|---|---|
| Status | Under environmental review |
| Status since | 17 Aug 2026 |
| Application filed | 13 Mar 2026 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Jsw Steel LTD |
| Land area | 70.7 acres (28.6 ha) |
| Project cost | ₹301 crore |
| Village / locality | Bursera |
| Taluk / tehsil | Chandrapura |
| District | Bokaro |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-02153 |
In context
93 applications in Bokaro since January 2022 are in the same category (Mining): 76 approved, 3 filed or under review, and 14 withdrawn, lapsed or rejected. The approved ones took a median of 41 days from filing to approval. At 70.7 acres, this one is larger than 75% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Bursera, Chandrapura, Bokaro, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Dugda Coking Coal Washery of 6 MTPA capacity by M/s JSW Steel Limited — withdrawn, 0 m away
- Dugda NLW Coal Washery of 2.5 MTPA — environmental approval granted, 1.7 km away
- Proposed Expansion by addition of 2x800 MW Coal Based Thermal Power Units to… — returned to applicant, 3.8 km away
- LILO of 132 KV Chandankyari - Jainamore Transmission Line at Dugda — in-principle approval, conditions pending, 5.3 km away
- Production of 33,412 TPA Granite gneiss through mechanized opencast mining… — environmental approval granted, 6.2 km away
- Expansion-Cum-Modernization of SAIL, Bokaro Steel Plant from 5.77 MTPA to 9.10… — under environmental review, 8.1 km away
- Expansion-Cum-Modernization of SAIL, Bokaro Steel Plant from 5.77 MTPA to 9.10… — cleared for impact study, 8.1 km away
- KUMHRI STONE MINE (Area 2.19 Ha.) — environmental approval granted, 8.9 km away
More from Jsw Steel LTD in Bokaro
- Dugda Coking Coal Washery of 6 MTPA capacity by M/s JSW Steel Limited — withdrawn
- Sitanala Coal Mine — environmental approval granted
- Parbatpur Centeral Coal Block — environmental approval granted
- Sitanala Coal Mine — lapsed
- Sitanala Coal Mine — lapsed
- Parbatpur Central Coal Block — not approved
8 Jsw Steel projects in Bokaro
All 97 Jsw Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.