Quick answers
What is this project?
Expansion-Cum-Modernization of SAIL, Bokaro Steel Plant from 5.77 MTPA to 9.10 MTPA Hot Metal and 5.006 MTPA to 8.806 MTPA Crude Steel is a proposed industrial project in Bokaro Steel City, Chas, Bokaro, Jharkhand. The site covers 5,762.5 acres.
Who is building it?
The applicant is Steel Authority of India LTD.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 5 May 2026), as of 27 Nov 2026.
Where is it?
In Bokaro Steel City, Chas, Bokaro, Jharkhand.
How big is it?
It has a stated cost of ₹32,795.4 crore and a site of 5,762.5 acres.
When was it filed?
The application was filed on 27 May 2024.
Project details
| Official title | Expansion-Cum-Modernization of SAIL, Bokaro Steel Plant from 5.77 MTPA to 9.10 MTPA Hot Metal and 5.006 MTPA to 8.806 MTPA Crude Steel at District Bokaro, Jharkhand |
|---|---|
| Status | Cleared for impact study |
| Status since | 5 May 2026 |
| Application filed | 27 May 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Steel Authority of India LTD |
| Land area | 5,762.5 acres (2,332 ha) |
| Project cost | ₹32,795.4 crore |
| Village / locality | Bokaro Steel City |
| Taluk / tehsil | Chas |
| District | Bokaro |
| State | Jharkhand |
| Location from | Site boundary on record |
| Our reference | WID-JH-00971 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 6 Oct 2026 | Under environmental review | 5,762.5 acres | ₹32,795.4 crore |
| Early planning filed 27 May 2024 (this page) | Cleared for impact study | 5,762.5 acres | ₹32,795.4 crore |
In context
27 applications in Bokaro since January 2022 are in the same category (Industry): 16 approved, 4 filed or under review, and 7 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 5,762.5 acres, this one is larger than 93% of them.
24 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Bokaro Steel City, Chas, Bokaro, Jharkhand. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion-Cum-Modernization of SAIL, Bokaro Steel Plant from 5.77 MTPA to 9.10… — under environmental review, 0 m away
- Expansion of Existing plant for total production of 0.6864 MTPA Sponge Iron,… — cleared for impact study, 2.5 km away
- Expansion of Existing plant for total production of 0.6864 MTPA Sponge Iron,… — withdrawn, 2.5 km away
- Initimation regarding change in Type of Boiler from AFBC to CFBC under "No… — initial checks, 2.7 km away
- Expansion of existing Sponge Iron plant from 54,000 TPA to 174,000 TPA,… — environmental approval granted, 2.7 km away
- Industrial project by Bokaro Spirits & Allied Industries Private Limited — environmental approval granted, 2.7 km away
- ENVIRONMENTAL CLEARANCE TO ENHANCE THE PRODUCTION OF M.S INGOT/BILLET FROM… — lapsed, 3 km away
- LILO of 132 KV Chandankyari - Jainamore Transmission Line at Dugda — in-principle approval, conditions pending, 3.2 km away
All 51 Steel Authority of India projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.