Quick answers
What is this project?
Expansion of Integrated Cement Plant - Clinker (2.1125 to 5.0 Million TPA), Cement (3.0 to 7.0 Million TPA), WHRS (14 to 28 MW) with no change in existing CPP (50 MW) at Villages: Itagi and Diggaon, Taluka: Chittapur, District: Kalaburagi, State: Karnataka by M/s. Orient Cement Limited is a proposed industrial project in Ch|Tapur, Chittapur, Kalaburagi, Karnataka. The site covers 657.3 acres.
Who is building it?
The applicant is Orient Cement Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 14 Sept 2023), as of 27 Nov 2026.
Where is it?
In Ch|Tapur, Chittapur, Kalaburagi, Karnataka.
How big is it?
It has a stated cost of ₹3,465.2 crore and a site of 657.3 acres.
When was it filed?
The application was filed on 11 Sept 2023.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Integrated Cement Plant - Clinker (2.1125 to 5.0 Million TPA), Cement (3.0…
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 14 Sept 2023 |
| Application filed | 11 Sept 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Orient Cement Limited |
| Land area | 657.3 acres (266 ha) |
| Project cost | ₹3,465.2 crore |
| Village / locality | Ch|Tapur |
| Taluk / tehsil | Chittapur |
| District | Kalaburagi |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-00942 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 12 Aug 2024 | Environmental approval granted | 657.3 acres | ₹3,465.2 crore |
| Early planning filed 11 Sept 2023 (this page) | Cleared for impact study | 657.3 acres | ₹3,465.2 crore |
In context
38 applications in Kalaburagi since January 2022 are in the same category (Industry): 23 approved, 9 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 657.3 acres, this one is larger than 76% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Ch|Tapur, Chittapur, Kalaburagi, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Integrated Cement Plant - Clinker (2.1125 to 5.0 Million TPA),… — environmental approval granted, 0 m away
- Expansion of Integrated Cement Plant - Clinker (2.0 to 5.0 Million TPA),… — withdrawn, 0 m away
- Proposed Cement Plant (Clinker- 2 MTPA; Cement 3.0 MTPA) and Captive Power… — environmental approval granted, 0 m away
- Increase in Production Capacity of Clinker from 20,00,000 TPA to 22,01,027 TPA… — initial checks, 100 m away
- Itagi Limestone Mine (ML Area: 519.0 Ha) with Expansion in Limestone… — environmental approval granted, 1.9 km away
- Itagi Limestone Mine (ML Area: 519.0 Ha) with Expansion in Limestone… — cleared for impact study, 2 km away
- Proposed Diggaon Limestone Block (ML Area – 786.32 ha) with Limestone… — environmental approval granted, 4.7 km away
- Proposed Diggaon Limestone Block (ML Area – 786.32 ha) with Limestone… — cleared for impact study, 4.7 km away
More from Orient Cement Limited in Kalaburagi
- Increase in Production Capacity of Clinker from 20,00,000 TPA to 22,01,027 TPA… — initial checks
- Itagi Limestone Mine (ML Area: 519.0 Ha) with Expansion in Limestone… — environmental approval granted
- Expansion of Integrated Cement Plant - Clinker (2.0 to 5.0 Million TPA),… — withdrawn
- Proposed Cement Plant (Clinker- 2 MTPA; Cement 3.0 MTPA) and Captive Power… — environmental approval granted
- Itagi Limestone Mine (ML Area: 519.0 Ha) with Expansion in Limestone… — cleared for impact study
7 Orient Cement projects in Kalaburagi
All 11 Orient Cement projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.