What is "Building Stone Quarry" of Sri. Bhimaraya T Sunagar?
"Building Stone Quarry" of Sri. Bhimaraya T Sunagar is an approved mining project in Ramapur, Sindgi, Vijayapura, Karnataka. The site covers 1.9 acres.
Who is building it?
The applicant is Bimaraya Sunagar.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 8 Mar 2023), as of 27 Nov 2026.
Where is it?
In Ramapur, Sindgi, Vijayapura, Karnataka.
How big is it?
It has a stated cost of ₹1.2 crore and a site of 1.9 acres.
When was it filed?
The application was filed on 8 Mar 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 8 Mar 2023 |
| Application filed | 8 Mar 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | Bimaraya Sunagar |
| Land area | 1.9 acres (0.8 ha) |
| Project cost | ₹1.2 crore |
| Village / locality | Ramapur |
| Taluk / tehsil | Sindgi |
| District | Vijayapura |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-01298 |
In context
37 applications in Vijayapura since January 2022 are in the same category (Mining): 31 approved, 2 filed or under review, and 4 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1.9 acres, this one is smaller than 86% of them.
No other mining lease on record is within 500 m of this site; 1 has applied within 5 km.
Where it is
Ramapur, Sindgi, Vijayapura, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Building Stone Quarry" of Sri. Hobu S/o Shankar Pawar — environmental approval granted, 2.2 km away
- Amendment to the Environmental Clearance Issued for Expanding the Sugar Plant,… — environmental approval granted, 9.2 km away
- Expansion of Sugar Plant From 3500 Tcd to 7500 Tcd, Co-Generation Power Plant… — lapsed, 9.2 km away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn, 9.2 km away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn, 9.2 km away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — withdrawn, 9.2 km away
- Expansion of Sugar Plant From 3500 Tcd to 7500 Tcd, Co-Generation Power Plant… — lapsed, 9.2 km away
- Distillery of 300 KLPD and Captive Power Plant of 6 MW and Expansion of the… — lapsed, 9.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.