Quick answers
What is this project?
Diversion of 1.465 Ha Forest land in F.Sy no 7,23&25 of Navagadda, 42A & 50A1A of Bogribail, 43A1A1 of Algeri, 102 A1A1A1A1A1A1A of Sakalben, Sy.no. 300A1A of Aversa, Syno.168 A1A & 169A1A1A1 of Harwada villages is a lapsed water and irrigation project in Algeri, Ankola, Uttara Kannada, Karnataka. The site covers 8.1 acres.
Who is building it?
The applicant is Karnataka Urban Water Supply and Drainage Board.
Has it been approved?
No. The application was lapsed on 5 Jul 2026, so it is no longer under consideration.
Where is it?
In Algeri, Ankola, Uttara Kannada, Karnataka.
How big is it?
It has a stated cost of ₹8 crore; a site of 8.1 acres and 3.6 acres (1.5 ha) of forest land.
When was it filed?
The application was filed on 6 Apr 2026.
Project details
| Official title | Diversion of 1.465 Ha Forest land in F.Sy no 7,23&25 of Navagadda, 42A & 50A1A of Bogribail, 43A1A1 of Algeri, 102 A1A1A1A1A1A1A of Sakalben, Sy.no. 300A1A of Aversa, Syno.168 A1A & 169A1A1A1 of Harwada villages in Ankola Taluk for Strengthening/Replacment of existing PSC Gravity main from navagadda to Mudga Ghat in favour of the Exectuive Engineer, Karnataka Urban Water Supply & Drainage Board, Division, karwar |
|---|---|
| Status | Lapsed |
| Status since | 5 Jul 2026 |
| Application filed | 6 Apr 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Karnataka Urban Water Supply and Drainage Board |
| Land area | 8.1 acres (3.3 ha) |
| Forest land | 3.6 acres (1.5 ha) |
| Project cost | ₹8 crore |
| Village / locality | Algeri |
| Taluk / tehsil | Ankola |
| District | Uttara Kannada |
| State | Karnataka |
| Location from | Site boundary on record |
| Our reference | WID-KA-06109 |
In context
63 applications in Uttara Kannada since January 2022 are in the same category (Water & irrigation): 2 approved, 48 filed or under review, and 13 withdrawn, lapsed or rejected. At 8.1 acres, this one is larger than 70% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Algeri, Ankola, Uttara Kannada, Karnataka. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Diversion of 1.6576 Ha. & Rediversion of 1.1621 Ha. forest land (totally… — more information requested, 1.3 km away
- Proposal for the Project Construction of Sewage treatment plant (STP) — lapsed, 2 km away
- Detailed Project Report for Proposal for Construction of 6kld Faecal Sludge… — initial checks, 2.2 km away
- Project for Construction of Sewage Treatment Plant(STP) at Baleguli Forest… — lapsed, 3.6 km away
- Construction of Residential House by Gopal Ramakrishna Nayhak — coastal clearance granted, 4 km away
- Construction of Residential House by Varad Dinakar Naik — lapsed, 4.1 km away
- Building stone Quarry of Laxmibai Subray Kamath Stone Crusher. — more information requested, 4.3 km away
- Request for Crz Clearance of Proposed Maintenance Dredging at Existing Fish… — coastal clearance granted, 5 km away
More from Karnataka Urban Water Supply and Drainage Board in Uttara Kannada
- Land Use Change / Laying of Overhead Transmission Line specific to Survey No.… — under forest review
- Vented Barrage Across Gangavali River at Honnalli to Supply Additional Water… — under forest review
- Diversion of 1.465 Ha Forest Land for Strengthening / Replacing Psc Gravity… — lapsed
- Diversion of 1.6576 Ha. & Rediversion of 1.1621 Ha. forest land (totally… — more information requested
5 Karnataka Urban Water Supply and Drainage Board projects in Uttara Kannada
All 10 Karnataka Urban Water Supply and Drainage Board projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.