Quick answers
What is this project?
Proposed 1X5 MVA Submerged Arc Furnace for Production of Ferro Alloys is a proposed industrial project in Chichala, Chandrapur, Maharashtra. The site covers 3 acres.
Who is building it?
The applicant is Destino Minerals & Metals Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Chichala, Chandrapur, Maharashtra.
How big is it?
It has a stated cost of ₹15.8 crore and a site of 3 acres.
When was it filed?
The application was filed on 4 Oct 2023.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Proposed 1X5 MVA Submerged Arc Furnace for Production of Ferro Alloys
Project details
| Status | More information requested |
|---|---|
| Status since | 2 Nov 2026 |
| Application filed | 4 Oct 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Destino Minerals & Metals Private Limited |
| Land area | 3 acres (1.2 ha) |
| Project cost | ₹15.8 crore |
| Village / locality | Chichala |
| Taluk / tehsil | Chandrapur |
| District | Chandrapur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-01497 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Early planning filed 7 Oct 2023 | Returned to applicant | 3 acres | ₹15.8 crore |
| New project filed 4 Oct 2023 (this page) | More information requested | 3 acres | ₹15.8 crore |
In context
55 applications in Chandrapur since January 2022 are in the same category (Industry): 38 approved, 11 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 3 acres, this one is smaller than 98% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Chichala, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed 1X5 MVA Submerged Arc Furnace for Production of Ferro Alloys — returned to applicant, 0 m away
- Application of Amendment in Consent to Operate With Change in Product in… — initial checks, 550 m away
- Application for Amendment in Cto With Decrease in Capacity Under Change in… — initial checks, 600 m away
- Amendment in Environmental Clearance for seeking review of applicability of… — environmental approval granted, 5 km away
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — cleared for impact study, 5.5 km away
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — cleared for impact study, 5.5 km away
- Expansion of Steel Melting Shop & Setting up of 1 x 20 MW Captive Power Plant… — environmental approval granted, 5.5 km away
- "Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to… — withdrawn, 5.5 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.