What is Developing? Open the mapMap

Cleared for impact studyIndustry · Chandrapur, Maharashtra

"Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to 5,28,000 TPA, MS Steel Ingots / Rolled products (finished) & Steel Ingots from 143,200 TPA to 7,50,000 TPA and Captive Power Plant from 20 MW to 80 MW"

"Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to 5,28,000 TPA, MS Steel Ingots / Rolled products (finished) & Steel Ingots from 143,200 TPA to 7,50,000 TPA and Captive Power Plant from 20 MW to 80 MW" is a proposed industrial project in Tadali, Chandrapur, Maharashtra. The site covers 116.8 acres. Its stated project cost is ₹1,051.2 crore. As of 27 Nov 2026, its status is “Cleared for impact study” (since 30 Sept 2026).

See it on the live map All projects in Chandrapur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

"Proposed Expansion of manufacturing plant with Sponge Iron from 90,000 TPA to 5,28,000 TPA, MS Steel Ingots / Rolled products (finished) & Steel Ingots from 143,200 TPA to 7,50,000 TPA and Captive Power Plant from 20 MW to 80 MW" is a proposed industrial project in Tadali, Chandrapur, Maharashtra. The site covers 116.8 acres.

Who is building it?

The applicant is Ofb Tech Limited.

Has it been approved?

Yes. Its status is “Cleared for impact study” (since 30 Sept 2026), as of 27 Nov 2026.

Where is it?

In Tadali, Chandrapur, Maharashtra.

How big is it?

It has a stated cost of ₹1,051.2 crore and a site of 116.8 acres.

When was it filed?

The application was filed on 14 Aug 2026.

Project details

StatusCleared for impact study
Status since30 Sept 2026
Application filed14 Aug 2026
Approval soughtEnvironmental approval
Application typeAmendment
SectorIndustry
ApplicantOfb Tech Limited
Land area116.8 acres (47.3 ha)
Project cost₹1,051.2 crore
Village / localityTadali
Taluk / tehsilChandrapur
DistrictChandrapur
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-13535

In context

55 applications in Chandrapur since January 2022 are in the same category (Industry): 38 approved, 11 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 116.8 acres, this one is smaller than 56% of them.

11 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Tadali, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 6 Ofb Tech projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.