Environmental approval grantedPower · Chandrapur, Maharashtra

Amendment in Environmental Clearance for seeking review of applicability of Sulphur dioxide standards and Exemption from Installation of FGD as per MoEF&CC Notification dated 11.07.2025 for 2×300 MW DIL Thermal Power Plant at Plot No-C6,C7,C8 Tadali Growth Centre, MIDC Tadali, Tal & Dist.-Chandrapur, Maharashtra

Amendment in Environmental Clearance for seeking review of applicability of Sulphur dioxide standards and Exemption from Installation of FGD as per MoEF&CC Notification dated 11.07.2025 for 2×300 MW DIL Thermal Power Plant at Plot No-C6,C7,C8 Tadali Growth Centre, MIDC Tadali, Tal & Dist.-Chandrapur, Maharashtra is an approved power project in Morwa, Chandrapur, Maharashtra. The site covers 480 acres. Its stated project cost is ₹3,964.3 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 12 Jun 2026).

See it on the live map All projects in Chandrapur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Amendment in Environmental Clearance for seeking review of applicability of Sulphur dioxide standards and Exemption from Installation of FGD as per MoEF&CC Notification dated 11.07.2025 for 2×300 MW DIL Thermal Power Plant at Plot No-C6,C7,C8 Tadali Growth Centre, MIDC Tadali, Tal & Dist.-Chandrapur, Maharashtra is an approved power project in Morwa, Chandrapur, Maharashtra. The site covers 480 acres.

Who is building it?

The applicant is Dhariwal Infrastructure Limited.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 12 Jun 2026), as of 27 Nov 2026.

Where is it?

In Morwa, Chandrapur, Maharashtra.

How big is it?

It has a stated cost of ₹3,964.3 crore and a site of 480 acres.

When was it filed?

The application was filed on 5 Feb 2026.

Project details

StatusEnvironmental approval granted
Status since12 Jun 2026
Application filed5 Feb 2026
Approval soughtEnvironmental approval
Application typeAmendment
SectorPower
ApplicantDhariwal Infrastructure Limited
Land area480 acres (194.3 ha)
Project cost₹3,964.3 crore
Village / localityMorwa
Taluk / tehsilChandrapur
DistrictChandrapur
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-12283

In context

10 applications in Chandrapur since January 2022 are in the same category (Power): 1 approved, 7 filed or under review, and 2 withdrawn, lapsed or rejected. At 480 acres, this one is larger than 60% of them.

16 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Morwa, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.