What is this project?
Expansion of Cement Plant (2.85 MTPA to 4.75 MTPA), Clinker Production (2.40 to 2.85 MTPA) and Captive Power Plant (55 to 70 MW) is an approved industrial project in Upparwahi, Korpana, Chandrapur, Maharashtra. The site covers 300 acres.
Who is building it?
The applicant is Ambuja Cement Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 28 Nov 2023), as of 27 Nov 2026.
Where is it?
In Upparwahi, Korpana, Chandrapur, Maharashtra.
How big is it?
It has a stated cost of ₹265 crore and a site of 300 acres.
When was it filed?
The application was filed on 5 Oct 2023.
Project details
| Official title | Expansion of Cement Plant (2.85 MTPA to 4.75 MTPA), Clinker Production (2.40 to 2.85 MTPA) and Captive Power Plant (55 to 70 MW) at Village: Upparwahi, Taluka: Korpana, District: Chandrapur (Maharashtra) by M/s. Maratha Cement Works (A Unit of Gujarat Ambuja Cement Limited). |
|---|---|
| Status | Environmental approval granted |
| Status since | 28 Nov 2023 |
| Application filed | 5 Oct 2023 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Industry |
| Applicant | Ambuja Cement Limited |
| Land area | 300 acres (121.4 ha) |
| Project cost | ₹265 crore |
| Village / locality | Upparwahi |
| Taluk / tehsil | Korpana |
| District | Chandrapur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-01598 |
In context
55 applications in Chandrapur since January 2022 are in the same category (Industry): 38 approved, 11 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 300 acres, this one is larger than 73% of them.
6 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Upparwahi, Korpana, Chandrapur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Integrated Cement Project (Clinker - 2.85 to 6.15 Million TPA,… — environmental approval granted, 1 km away
- Diversion of 0.66Ha. Forest Land for installation of 4G Mobile Towers for 4G… — lapsed, 2.8 km away
- Expansion in Limestone Production Capacity from 1.5 million TPA to 3.5 million… — more information requested, 3 km away
- Expansion in Limestone Production Capacity from 1.5 million TPA to 3.5 million… — environmental approval granted, 3 km away
- Diversion of Forest Land for Laying Optical Fiber Cable Within Row of the… — lapsed, 3.8 km away
- Expansion in Limestone Production Capacity from 2.0 Million TPA to 3.5 Million… — lapsed, 4.1 km away
- Modification in existing Deshaled Coal Crushing Unit to 2.0 MTPA Wet Coal… — environmental approval granted, 7.7 km away
- Modification in existing 2.0 MTPA Deshaled Coal Crushing Unit to 2.0 MTPA Wet… — cleared for impact study, 7.7 km away
More from Ambuja Cement Limited in Chandrapur
- Expansion of Integrated Cement Project (Clinker - 2.85 to 6.15 Million TPA,… — environmental approval granted
All 26 Ambuja Cement projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.