Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 19 May 2025 |
| Application filed | 14 Aug 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | The Tata Power Co. Ltd. |
| Land area | 1,315.6 acres (532.4 ha) |
| Project cost | ₹4,743.6 crore |
| Village / locality | Sawale |
| Taluk / tehsil | Mawal |
| District | Pune |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-03530 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 14 Aug 2024 (this page) | Environmental approval granted | 1,315.6 acres | ₹4,743.6 crore |
| Early planning filed 7 Aug 2023 | Cleared for impact study | 1,315.6 acres | ₹4,743.6 crore |
In context
45 applications in Pune since January 2022 are in the same category (Water & irrigation): 21 approved, 15 filed or under review, and 9 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 1,315.6 acres, this one is smaller than 57% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Sawale, Mawal, Pune, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Bhivpuri Off-Stream Open Loop Pumped Storage Project (1000 MW) — forest land use approved, 0 m away
- Bhivpuri Off-Stream Open Loop Pumped Storage Project (1000 MW) — cleared for impact study, 0 m away
- Saidongar-1 Pumped Storage Project (3000 MW) — cleared for impact study, 4.8 km away
- Proposed Expansion in Environment Clearance of "Centre for Perfect Health" — environmental approval granted, 9 km away
- Proposed Expansion in Environment Clearance of "Centre for Perfect Health" — cleared for impact study, 9 km away
- Pimpalpada Savale Pumped Storage Project — initial checks, 9.1 km away
- Pimpalpada Savale Pumped Storage Project — under environmental review, 9.1 km away
- Pimpalpada Savale Pumped Storage Project — initial checks, 9.1 km away
More from The Tata Power Co. Ltd. in Pune
- Shirawta Off Stream Open Loop Pumped Storage Project (1800 MW) — environmental approval granted
- Shirawta Off Stream Open Loop Pumped Storage Project (1800 MW) — in-principle approval, conditions pending
- Shirawta Off Stream Open Loop Pumped Storage Project (1800 MW) — cleared for impact study
- Bhivpuri Off-Stream Open Loop Pumped Storage Project (1000 MW) — forest land use approved
- Shirawta Off Stream Open Loop Pumped Storage Project (1800 MW) — under forest review
- Shirawta Off Stream Open Loop Pumped Storage Project (1800 MW) — cleared for impact study
8 The Tata Power Co projects in Pune
All 25 The Tata Power Co projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.