| Status | Environmental approval granted |
|---|---|
| Status since | 12 Sept 2025 |
| Application filed | 24 May 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Web Werks India Private Limited |
| Use | IT / offices |
| Land area | 4.8 acres (1.9 ha) |
| Built-up area | 1,38,194 m² (14,87,506 sq ft) |
| Plot area | 19,350 m² (2,08,281 sq ft) |
| Project cost | ₹3,775 crore |
| Village / locality | Rabade |
| Taluk / tehsil | Thane |
| District | Thane |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-04214 |
In context
1,540 applications in Thane since January 2022 are in the same category (Buildings & townships): 1,001 approved, 200 filed or under review, and 339 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 4.8 acres, this one is larger than 52% of them.
208 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Rabade, Thane, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion in Data centre project by M/s. GARGANTUAN INDUSTRIAL SPACE… — lapsed, 550 m away
- Proposed Expansion in Data centre project by M/s. GARGANTUAN INDUSTRIAL SPACE… — environmental approval granted, 550 m away
- Expansion in for "Data Center" at Plot No. R-847/2 & R-979, R-847/3,… — environmental approval granted, 700 m away
- Expansion for "Data Center" at Plot No. R-847/2 & R-979, R-847/3, R-847/3/1,… — environmental approval granted, 700 m away
- Expansion of Proposed "Data Center" AT R-847/2 & Plot No: R-979, T.T.C.… — environmental approval granted, 750 m away
- Expansion of Proposed "Data Center" AT R-847/2 & Plot No: R-979, T.T.C.… — withdrawn, 750 m away
- Expansion of Proposed "Data Center" AT R-847/2 & Plot No: R-979, T.T.C.… — environmental approval granted, 750 m away
- Proposed expansion project for manufacturing of Synthetic Organic Chemicals… — cleared for impact study, 1.2 km away