Quick answers
What is this project?
Expansion of Existing Steel Plant from 700 TPD to 2000 TPD M.S. Billets, 600 TPD Strips RM for MS Coils/MS Sheets/MS Pipes/MS Flats/MS Angles/MS Square Bars/MS Channels/MS Beams/MS Plates, 1400 TPD RM for TMT Bars/Round Bars/Wire Rods by M/s. Gajkesari Steels & Alloys Pvt. Ltd is a proposed industrial project in Jalna, Maharashtra. The site covers 12.3 acres.
Who is building it?
The applicant is Gajkesari Steels and Allloys PVT LTD.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 29 Apr 2025), as of 27 Nov 2026.
Where is it?
In Jalna, Maharashtra.
How big is it?
It has a stated cost of ₹425 crore and a site of 12.3 acres.
When was it filed?
The application was filed on 29 Apr 2025.
Project details
| Official title | Expansion of Existing Steel Plant from 700 TPD to 2000 TPD M.S. Billets, 600 TPD Strips RM for MS Coils/MS Sheets/MS Pipes/MS Flats/MS Angles/MS Square Bars/MS Channels/MS Beams/MS Plates, 1400 TPD RM for TMT Bars/Round Bars/Wire Rods along with Installation of 1 x 13 MVA SAF to manufacture 36,000 TPA (FeMn/ SiMn) at Plot No. F-18 & F-19, Phase -II Additional MIDC, Gut No. 33, Daregaon ,Taluka & Dist: Jalna 431203 (Maharashtra) over an area 4.96 ha. by M/s. Gajkesari Steels & Alloys Pvt. Ltd. |
|---|---|
| Status | Cleared for impact study |
| Status since | 29 Apr 2025 |
| Application filed | 29 Apr 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Gajkesari Steels and Allloys PVT LTD |
| Land area | 12.3 acres (5 ha) |
| Project cost | ₹425 crore |
| Village / locality | Jalna |
| Taluk / tehsil | Jalna |
| District | Jalna |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-07559 |
In context
36 applications in Jalna since January 2022 are in the same category (Industry): 26 approved, 4 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 12.3 acres, this one is smaller than 61% of them.
29 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jalna, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Existing Steel plant for M.S. Billets from 700 TPD to 2000 TPD,… — lapsed, 0 m away
- Manufacture of TMT Bar with capacity 500 TPD Stand-alone Rolling Mill (Existing) — cleared for impact study, 200 m away
- Manufacture of M.S Round Bars, Flat Bars, Square Bars & M.S. Angles with… — cleared for impact study, 200 m away
- Proposed Expansion in Production of MS Billets -750 TPD to 2000 TPD and… — environmental approval granted, 300 m away
- Proposed Expansion in Production of MS Billets -750 TPD to 2000 TPD and… — cleared for impact study, 300 m away
- Modernization Cum Expansion of MS Billets Production from 1,58,400 TPA to… — lapsed, 400 m away
- Modernization Cum Expansion of MS Billets Production from 1,58,400 TPA to… — cleared for impact study, 400 m away
- Manufacture of TMT Bar with capacity 1000 TPD Stand-alone Rolling Mill… — cleared for impact study, 550 m away
More from Gajkesari Steels and Allloys PVT LTD in Jalna
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.