Quick answers
What is this project?
Modernization Cum Expansion of MS Billets Production from 1,58,400 TPA to 4,98,960 TPA, TMT Bars production from 1,58,400 TPA to 4,98,960 TPA by Metarolls Ispat Pvt. Ltd is a proposed industrial project in Jalna, Maharashtra. The site covers 18.9 acres.
Who is building it?
The applicant is Metarolls Ispat Private Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 12 Sept 2023), as of 27 Nov 2026.
Where is it?
In Jalna, Maharashtra.
How big is it?
It has a stated cost of ₹328.5 crore and a site of 18.9 acres.
When was it filed?
The application was filed on 13 Jul 2023.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 12 Sept 2023 |
| Application filed | 13 Jul 2023 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Industry |
| Applicant | Metarolls Ispat Private Limited |
| Land area | 18.9 acres (7.6 ha) |
| Project cost | ₹328.5 crore |
| Village / locality | Jalna |
| Taluk / tehsil | Jalna |
| District | Jalna |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-01773 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 25 Dec 2023 | Lapsed | 18.9 acres | ₹328.5 crore |
| Amendment filed 13 Jul 2023 (this page) | Cleared for impact study | 18.9 acres | ₹328.5 crore |
In context
36 applications in Jalna since January 2022 are in the same category (Industry): 26 approved, 4 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 18.9 acres, this one is smaller than 53% of them.
28 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Jalna, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Modernization Cum Expansion of MS Billets Production from 1,58,400 TPA to… — lapsed, 0 m away
- Ferro-Alloys unit to manufacture 66,000 TPA (FeMn/ SiMn) by Installing 2x18… — environmental approval granted, 200 m away
- Manufacture of TMT Bar with capacity 500 TPD Stand-alone Rolling Mill (Existing) — cleared for impact study, 300 m away
- Expansion of Existing Steel plant for M.S. Billets from 700 TPD to 2000 TPD,… — lapsed, 400 m away
- Expansion of Existing Steel Plant from 700 TPD to 2000 TPD M.S. Billets, 600… — cleared for impact study, 400 m away
- Manufacture of TMT Bar with capacity 1000 TPD Stand-alone Rolling Mill… — cleared for impact study, 400 m away
- Ferro-Alloys unit to manufacture 66,000 TPA (FeMn/ SiMn) by Installing 2x18… — cleared for impact study, 450 m away
- Modification and Expansion of Existing Scrap Processing Unit with Addition of… — cleared for impact study, 450 m away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.