Proposed Expansion of Sugar Plant from 3500 TCD to 10000 TCD & Cogeneration Power Plant from 15MW to 40MW at Kanadkhed, Tal. Purna, Dist. Parbhani by M/s. Baliraja Sakhar Karkhana Limited is an approved industrial project in Kanad Kheda, Purna, Parbhani, Maharashtra. The site covers 72.6 acres.
Who is building it?
The applicant is Baliraja Sakhar Karkhana Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 12 Feb 2026), as of 27 Nov 2026.
Where is it?
In Kanad Kheda, Purna, Parbhani, Maharashtra.
How big is it?
It has a stated cost of ₹373.6 crore and a site of 72.6 acres.
When was it filed?
The application was filed on 21 Jul 2025.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 12 Feb 2026 |
| Application filed | 21 Jul 2025 |
| Approval sought | Environmental approval |
| Application type | Expansion |
| Sector | Industry |
| Applicant | Baliraja Sakhar Karkhana Limited |
| Land area | 72.6 acres (29.4 ha) |
| Project cost | ₹373.6 crore |
| Village / locality | Kanad Kheda |
| Taluk / tehsil | Purna |
| District | Parbhani |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-10465 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 21 Jul 2025 (this page) | Environmental approval granted | 72.6 acres | ₹373.6 crore |
| Early planning filed 22 Nov 2024 | Cleared for impact study | 72.6 acres | ₹373.6 crore |
In context
12 applications in Parbhani since January 2022 are in the same category (Industry): 9 approved, 1 filed or under review, and 2 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 72.6 acres, this one is smaller than 58% of them.
7 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kanad Kheda, Purna, Parbhani, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Expansion of Sugar Plant from 3500 TCD to 10000 TCD & Cogeneration… — cleared for impact study, 0 m away
- Expansion of Nila Sand Ghat, Parbhani — environmental approval granted, 2.9 km away
- Nila Sand Ghat, Parbhani — lapsed, 2.9 km away
- Nila Sand Ghat, Parbhani — environmental approval granted, 2.9 km away
- Mining project by M/s. Balaji Stone Crusher through Mr. Pravin Satyanarayan… — not approved, 3.4 km away
- Expansion Of Kankhed Sand Ghat, Parbhani — environmental approval granted, 3.6 km away
- Kankhed Sand Ghat — lapsed, 3.6 km away
- Kankhed Sand Ghat, Parbhani — environmental approval granted, 3.6 km away