Quick answers
What is Expansion of Nila Sand Ghat, Parbhani?
Expansion of Nila Sand Ghat, Parbhani is an approved mining project in Kanad Kheda, Purna, Parbhani, Maharashtra. The site covers 8.2 acres.
Who is building it?
The applicant is District Mining Officer.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 21 Jan 2026), as of 27 Nov 2026.
Where is it?
In Kanad Kheda, Purna, Parbhani, Maharashtra.
How big is it?
It has a stated cost of ₹34 lakh and a site of 8.2 acres.
When was it filed?
The application was filed on 3 Jan 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 21 Jan 2026 |
| Application filed | 3 Jan 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Mining |
| Applicant | District Mining Officer |
| Land area | 8.2 acres (3.3 ha) |
| Project cost | ₹34 lakh |
| Village / locality | Kanad Kheda |
| Taluk / tehsil | Purna |
| District | Parbhani |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-13328 |
In context
172 applications in Parbhani since January 2022 are in the same category (Mining): 147 approved, 0 filed or under review, and 25 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 8.2 acres, this one is larger than 80% of them.
No other mining lease on record is within 500 m of this site; 10 have applied within 5 km.
Where it is
Kanad Kheda, Purna, Parbhani, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Nila Sand Ghat, Parbhani — lapsed, 0 m away
- Nila Sand Ghat, Parbhani — environmental approval granted, 0 m away
- Expansion Of Kankhed Sand Ghat, Parbhani — environmental approval granted, 2.5 km away
- Kankhed Sand Ghat — lapsed, 2.5 km away
- Kankhed Sand Ghat, Parbhani — environmental approval granted, 2.5 km away
- Proposed Expansion of Sugar Plant from 3500 TCD to 10000 TCD & Cogeneration… — environmental approval granted, 2.9 km away
- Proposed Expansion of Sugar Plant from 3500 TCD to 10000 TCD & Cogeneration… — cleared for impact study, 2.9 km away
- Transfer of Environmental Clearance of Kantheshwar Sandghat from VANDANA… — environmental approval granted, 4.2 km away
More from District Mining Officer in Parbhani
- Expansion of Ravrajur Sand Ghat, Parbhani — environmental approval granted
- Expansion of Gunj Sand Ghat, Parbhani — environmental approval granted
- Expansion of Mithapur Sand Ghat, Parbhani — environmental approval granted
- Expansion of Sawangithadi Sand Ghat, Parbhani — environmental approval granted
- Expansion Of Kankhed Sand Ghat, Parbhani — environmental approval granted
- Expansion of Dhanewadi Sand Ghat, Parbhani — environmental approval granted
All 27 District Mining Officer, Maharashtra projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.