What is this project?
Proposed Industrial Shed Construction for Multimodal Park (Industrial/ Warehousing/ Logistics) as "XSIO Logistics Parks Three" by M/s. XSIO LOGISTICS PARKS PVT. LTD is an approved industrial building project in Tarsi, Nagpur (Rural), Nagpur, Maharashtra. The site covers 29.7 acres.
Who is building it?
The applicant is Xsio Logistics Parks Private Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 5 Jul 2026), as of 27 Nov 2026.
Where is it?
In Tarsi, Nagpur (Rural), Nagpur, Maharashtra.
How big is it?
It has a stated cost of ₹245 crore and a site of 29.7 acres.
When was it filed?
The application was filed on 6 Jan 2026.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 5 Jul 2026 |
| Application filed | 6 Jan 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Xsio Logistics Parks Private Limited |
| Use | Industrial |
| Land area | 29.7 acres (12 ha) |
| Built-up area | 91,311 m² (9,82,862 sq ft) |
| Project cost | ₹245 crore |
| Village / locality | Tarsi |
| Taluk / tehsil | Nagpur (Rural) |
| District | Nagpur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-11756 |
In context
168 applications in Nagpur since January 2022 are in the same category (Buildings & townships): 128 approved, 22 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 29.7 acres, this one is larger than 70% of them.
30 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Tarsi, Nagpur (Rural), Nagpur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Greenfield Project for PET Tirecord Manufacturing Plant having… — environmental approval granted, 700 m away
- Proposed Greenfield Project for PET Tirecord Manufacturing Plant having… — cleared for impact study, 700 m away
- Addl. Butibori I.A. Village Tarsi Survey No 148 — lapsed, 750 m away
- Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line… — environmental approval granted, 1.2 km away
- Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line… — environmental approval granted, 1.2 km away
- Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line… — initial checks, 1.2 km away
- Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line… — environmental approval granted, 1.2 km away
- Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line… — cleared for impact study, 1.2 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.