What is Developing? Open the mapMap

Environmental approval grantedBuildings & townships · Nagpur, Maharashtra

Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line plant by M/s. Avaada Electro Pvt. Ltd., at Plot No. A-67, MIDC Road, Additional Butibori Industrial area, Nagpur, Nagpur, Maharashtra, 441108

Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line plant by M/s. Avaada Electro Pvt. Ltd., at Plot No. A-67, MIDC Road, Additional Butibori Industrial area, Nagpur, Nagpur, Maharashtra, 441108 is an approved industrial building project in Dhawalpeth, Nagpur (Rural), Nagpur, Maharashtra. The site covers 179.8 acres. Its stated project cost is ₹4,139.8 crore. As of 27 Nov 2026, its status is “Environmental approval granted” (since 12 Sept 2025).

See it on the live map All projects in Nagpur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line plant by M/s. Avaada Electro Pvt. Ltd., at Plot No. A-67, MIDC Road, Additional Butibori Industrial area, Nagpur, Nagpur, Maharashtra, 441108 is an approved industrial building project in Dhawalpeth, Nagpur (Rural), Nagpur, Maharashtra. The site covers 179.8 acres.

Who is building it?

The applicant is Avaada Electro Private Limited.

Has it been approved?

Yes. Its status is “Environmental approval granted” (since 12 Sept 2025), as of 27 Nov 2026.

Where is it?

In Dhawalpeth, Nagpur (Rural), Nagpur, Maharashtra.

How big is it?

It has a stated cost of ₹4,139.8 crore and a site of 179.8 acres.

When was it filed?

The application was filed on 7 Jul 2025.

One of 5 filings for this project. The project's main page, with every filing and where each stands: Expansion in Proposed installation of Integrated 6 GW cell and 5GW module line plant by…

Project details

StatusEnvironmental approval granted
Status since12 Sept 2025
Application filed7 Jul 2025
Approval soughtEnvironmental approval
Application typeExpansion
SectorBuildings & townships
ApplicantAvaada Electro Private Limited
UseIndustrial
Land area179.8 acres (72.8 ha)
Plot area7,27,500 m² (78,30,737 sq ft)
Project cost₹4,139.8 crore
Village / localityDhawalpeth
Taluk / tehsilNagpur (Rural)
DistrictNagpur
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-09147

All filings for this project

This project has 5 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Amendment filed 2 Jan 2026Environmental approval granted130.2 acres₹4,139.8 crore
Ownership transfer filed 15 Oct 2025Environmental approval granted179.8 acres₹4,139.8 crore
New project filed 20 Sept 2025Initial checks179.8 acres₹4,139.8 crore
Expansion filed 7 Jul 2025 (this page)Environmental approval granted179.8 acres₹4,139.8 crore
Early planning filed 27 May 2025Cleared for impact study179.8 acres₹4,139.8 crore

In context

168 applications in Nagpur since January 2022 are in the same category (Buildings & townships): 128 approved, 22 filed or under review, and 18 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 179.8 acres, this one is larger than 93% of them.

26 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Dhawalpeth, Nagpur (Rural), Nagpur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

More from Avaada Electro Private Limited in Nagpur

6 Avaada Electro projects in Nagpur
All 9 Avaada Electro projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.