Quick answers
What is this project?
Transfer of EC/Change in Name subsequent to NCLT Order from Adani Cementation Limited to Adani Cement Industries Ltd. for Berthing Jetty, Conveyor Corridor with Backup Storage Facilities and Approach Road to Cement Grinding Unit & Fly ash/Slag Processing Unit along Amba River is a proposed port and coastal project in Shahabaj, Alibag, Raigarh, Maharashtra. The site covers 39.2 acres.
Who is building it?
The applicant is Adani Cement Industries Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Shahabaj, Alibag, Raigarh, Maharashtra.
How big is it?
It has a stated cost of ₹172 crore and a site of 39.2 acres.
When was it filed?
The application was filed on 18 May 2026.
Project details
| Official title | Transfer of EC/Change in Name subsequent to NCLT Order from Adani Cementation Limited to Adani Cement Industries Ltd. for Berthing Jetty, Conveyor Corridor with Backup Storage Facilities and Approach Road to Cement Grinding Unit & Fly ash/Slag Processing Unit along Amba River at village Shahbaj and Shahpur, Taluka Alibag, District Raigad, Maharashtra |
|---|---|
| Status | More information requested |
| Status since | 3 Nov 2026 |
| Application filed | 18 May 2026 |
| Approval sought | Environmental approval |
| Application type | Ownership transfer |
| Sector | Ports & coast |
| Applicant | Adani Cement Industries Limited |
| Land area | 39.2 acres (15.9 ha) |
| Project cost | ₹172 crore |
| Village / locality | Shahabaj |
| Taluk / tehsil | Alibag |
| District | Raigarh |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-13280 |
In context
54 applications in Raigarh since January 2022 are in the same category (Ports & coast): 25 approved, 13 filed or under review, and 16 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 39.2 acres, this one is smaller than 51% of them.
23 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Shahabaj, Alibag, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of EC/Change in Name subsequent to NCLT Order from Adani Cementation… — lapsed, 150 m away
- Greenfield Cement Grinding Unit with Cement Production Capacity of 4.5 Million… — environmental approval granted, 200 m away
- Request for Change in User Agency Name from Adani Cementation Limited to Adani… — initial checks, 250 m away
- 6.0 MTPA Cement Blending & Grinding Unit (OPC, PPC, PSC, GGBS, SSC & Composite… — under environmental review, 700 m away
- Proposed construction of Conveyor Belt by JSW Steel Ltd. — more information requested, 1.1 km away
- Greenfield Cement Grinding Unit with Cement Production Capacity of 4.5 Million… — environmental approval granted, 1.2 km away
- Proposed Expansion of Dharamtar Jetty facility (Phase III) — environmental approval granted, 1.2 km away
- Proposed Expansion of Dharamtar Jetty facility (Phase III) — lapsed, 1.2 km away
More from Adani Cement Industries Limited in Raigarh
- Request for Change in User Agency Name from Adani Cementation Limited to Adani… — initial checks
- Transfer of EC/Change in Name subsequent to NCLT Order from Adani Cementation… — lapsed
All 3 Adani Cement Industries projects across India
About this information