Greenfield Cement Grinding Unit with Cement Production Capacity of 4.5 Million Metric Tons Per Annum (MMTPA) and 0.5 Million Metric Tons Per Annum (MMTPA), Fly Ash / Slag Processing Unit by M/s. Adani Cementation Limited is an approved industrial project in Shahabaj, Alibag, Raigarh, Maharashtra. The site covers 74.1 acres.
Who is building it?
The applicant is Adani Cementation Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 13 Sept 2024), as of 27 Nov 2026.
Where is it?
In Shahabaj, Alibag, Raigarh, Maharashtra.
How big is it?
It has a stated cost of ₹990 crore and a site of 74.1 acres.
When was it filed?
The application was filed on 9 Apr 2024.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Greenfield Cement Grinding Unit with Cement Production Capacity of 4.5 Million Metric…
Project details
| Official title | Greenfield Cement Grinding Unit with Cement Production Capacity of 4.5 Million Metric Tons Per Annum (MMTPA) and 0.5 Million Metric Tons Per Annum (MMTPA), Fly Ash / Slag Processing Unit at Village: Shahbaj, Taluka: Alibag, District: Raigad, Maharashtra by M/s. Adani Cementation Limited |
|---|---|
| Status | Environmental approval granted |
| Status since | 13 Sept 2024 |
| Application filed | 9 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Industry |
| Applicant | Adani Cementation Limited |
| Land area | 74.1 acres (30 ha) |
| Project cost | ₹990 crore |
| Village / locality | Shahabaj |
| Taluk / tehsil | Alibag |
| District | Raigarh |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-00389 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 28 Oct 2024 | Environmental approval granted | 148.1 acres | ₹990 crore |
| New project filed 9 Apr 2024 (this page) | Environmental approval granted | 74.1 acres | ₹990 crore |
In context
260 applications in Raigarh since January 2022 are in the same category (Industry): 152 approved, 67 filed or under review, and 41 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 74.1 acres, this one is larger than 87% of them.
22 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Shahabaj, Alibag, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of EC/Change in Name subsequent to NCLT Order from Adani Cementation… — lapsed, 1.1 km away
- Greenfield Cement Grinding Unit with Cement Production Capacity of 4.5 Million… — environmental approval granted, 1.1 km away
- Transfer of EC/Change in Name subsequent to NCLT Order from Adani Cementation… — more information requested, 1.2 km away
- 6.0 MTPA Cement Blending & Grinding Unit (OPC, PPC, PSC, GGBS, SSC & Composite… — under environmental review, 1.4 km away
- Proposed construction of Conveyor Belt by JSW Steel Ltd. — more information requested, 1.4 km away
- Proposed Expansion of Dharamtar Jetty facility (Phase III) — environmental approval granted, 1.4 km away
- Proposed Expansion of Dharamtar Jetty facility (Phase III) — lapsed, 1.4 km away
- Proposed Expansion of Dharamtar Jetty facility (Phase III) — cleared for impact study, 1.4 km away
More from Adani Cementation Limited in Raigarh
- Berthing Jetty, Conveyor Corridor with Backup Storage Facilities and Approach… — environmental approval granted
3 Adani Cementation projects in Raigarh
All 5 Adani Cementation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.