What is Proposed Expansion of Dharamtar Jetty facility (Phase III)?

Proposed Expansion of Dharamtar Jetty facility (Phase III) is a lapsed building project in Wave, Pen, Raigarh, Maharashtra. The site covers 144.8 acres.

Who is building it?

The applicant is JSW Dharamtar Port Private Limited.

Has it been approved?

No. The application was lapsed on 12 Mar 2026, so it is no longer under consideration.

Where is it?

In Wave, Pen, Raigarh, Maharashtra.

How big is it?

It has a stated cost of ₹2,500 crore and a site of 144.8 acres.

When was it filed?

The application was filed on 24 Sept 2025.

One of 3 filings for this project. The project's main page, with every filing and where each stands: Proposed Expansion of Dharamtar Jetty facility (Phase III)

Project details

Official titleProposed Expansion of Dharamtar Jetty facility (Phase III) in village Dolvi of District Raigad, Maharashtra
StatusLapsed
Status since12 Mar 2026
Application filed24 Sept 2025
Approval soughtCoastal review
Application typeNew project
SectorBuildings & townships
ApplicantJSW Dharamtar Port Private Limited
Land area144.8 acres (58.6 ha)
Project cost₹2,500 crore
Village / localityWave
Taluk / tehsilPen
DistrictRaigarh
StateMaharashtra
Location fromSite boundary on record
Our referenceWID-MH-17477

All filings for this project

This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
Expansion filed 11 Dec 2025Environmental approval granted144.8 acres₹2,500 crore
New project filed 24 Sept 2025 (this page)Lapsed144.8 acres₹2,500 crore
Early planning filed 21 Feb 2024Cleared for impact study144.8 acres₹2,500 crore

What the filings say

What is planned

JSW Dharamtar Port Private Limited (JSWDPPL) proposes the Phase III expansion of its existing jetty facility on the right bank of the Amba river and Dharamtar creek. The facility currently handles raw materials and products for the JSW Steel and JSW Cement plants at Dolvi. The expansion aims to increase cargo handling capacity from 33.95 million tonnes per annum (MTPA) to 54 MTPA (with some documents citing up to 57 MTPA). This increase is intended to support the expansion of the Dolvi steel plant to 15 MTPA.

The project involves utilizing the remaining 700 metres of approved berth length (Berths 10 to 13) in addition to the existing 1,050 metres (Berths 1 to 9). The applicant states that no additional construction is required beyond the expansion of cargo handling infrastructure. Key components of the expansion include:

Cargo Handling Details

CommodityExisting (MTPA)Total After Expansion (MTPA)
Iron Bearing Raw Material (IBRM)17.026.0
Coal Bearing Raw Material (CBRM)8.0010.0
Fluxes3.007.00
Finished Steel Products/Scrap2.503.00
Cement & Clinker1.604.00
LPG, Propane, Butane-3.00
Edible Oil & Liquid Cargo-1.00
Containers0.851.00
Fertilizer, FRM, Gypsum-1.00
Grand Total33.9557.0

Layout and design

The project is located in a Coastal Regulation Zone (CRZ) IVB area. The seabed at the site is highly undulated, consisting of soft silty clay sediments followed by hard strata at depths of 0 to 6 metres. Ship tranquility studies indicate that the meandering river and surrounding mangroves damp wave heights to less than 0.4 metres, providing adequate conditions for ships at berth. The layout includes covered storage yards (Yard A and Yard B), stacker-reclaimers, and a cross-country conveyor system to transport materials directly to the steel and cement plants.

Land and surroundings

The project occupies 58.6 hectares (144.8 acres) of existing jetty and backup area. The surrounding land use is approximately 49.6% vegetation and 30.7% agriculture. The applicant states that no forest land diversion or tree cutting is involved. Mangroves, including species like Avicennia marina and Sonneratia alba, are present along the creek banks near the northern side of the jetty. Baseline studies conducted between October and December 2023 found that ambient air quality and noise levels were generally within prescribed norms, though higher particulate matter was noted near industrial activity and heavy traffic on National Highway 66.

Water, power and access

Water requirement is expected to increase from 30 cubic metres per hour to 45 cubic metres per hour, sourced from the existing allocation from the Amba river at Nagothane. Domestic sewage will be treated in an existing 50-kilolitre-per-day sewage treatment plant, with treated water used for gardening. Power requirement for the expansion is 10,000 KVA, to be sourced from the Maharashtra State Electricity Distribution Co. Ltd. Access to the site is via the Alibaug-Pen Road and the Mumbai-Goa National Highway 66. A traffic study estimated that the expansion requires 576 equivalent car spaces (ECS) for parking, while 854 ECS are currently available.

Environmental safeguards

To mitigate dust, the applicant proposes covering bulk cargo with tarpaulin sheets, using closed conveyor galleries with dust suppression systems, and regular water sprinkling on stockpiles. Dredging will utilize cutter suction technology to minimize turbidity, and silt curtains will be deployed. An oil spill contingency plan has been prepared for a worst-case discharge of 16 tons of fuel, with response preparedness for up to 700 tons. The existing greenbelt of 10,619.1 square metres will be expanded by 1,383.4 square metres, bringing the total to 12,002.5 square metres.

What was said at the public hearing

A public hearing was held on 22 August 2025 at the JSW Jetty Truck Parking area. Key points raised included:

Expansion of Dharamtar Jetty Facility (Phase III) site plan and layout

2 drawings from the project's filings. Sign in free to see them.

Expansion of Dharamtar Jetty Facility (Phase III): Phase 3 expansion layout: berths, storage sheds, and conveyor systems (preview)🔒 Sign in free to see it
Phase 3 expansion layout: berths, storage sheds, and conveyor systems
Expansion of Dharamtar Jetty Facility (Phase III): Specific location map showing existing and proposed berths and storage systems (preview)🔒 Sign in free to see it
Specific location map showing existing and proposed berths and storage systems

In context

674 applications in Raigarh since January 2022 are in the same category (Buildings & townships): 403 approved, 85 filed or under review, and 186 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 144.8 acres, this one is larger than 95% of them.

22 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Wave, Pen, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 3 JSW Dharamtar Port projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.