Quick answers
What is this project?
Diversion of Forest Land for Widening and Concreting of Existing Bela-Thana (Mdr-36) Road From Chainage 12 500 to 20 500 in Taluka Umred, District Nagpur, Maharashtra is a proposed road project in Thana, Umred, Nagpur, Maharashtra. The site covers 1,946.1 acres.
Who is building it?
The applicant is Vilesh R Amrute.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Thana, Umred, Nagpur, Maharashtra.
How big is it?
It has a stated cost of ₹2 crore; a site of 1,946.1 acres and 2.4 acres (1 ha) of forest land.
When was it filed?
The application was filed on 5 May 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 4 Sept 2026 |
| Application filed | 5 May 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Vilesh R Amrute |
| Land area | 1,946.1 acres (787.6 ha) |
| Forest land | 2.4 acres (1 ha) |
| Project cost | ₹2 crore |
| Village / locality | Thana |
| Taluk / tehsil | Umred |
| District | Nagpur |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-14456 |
In context
31 applications in Nagpur since January 2022 are in the same category (Roads & highways): 1 approved, 23 filed or under review, and 7 withdrawn, lapsed or rejected. At 1,946.1 acres, this one is larger than 83% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Thana, Umred, Nagpur, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed SSP/Fortified (Zincated/Boronated) SSP, GSSP/Fortified… — environmental approval granted, 3.7 km away
- Diversion of 16.1403 Ha of Forest Land for Construction of 220 kV D/C… — under forest review, 5.3 km away
- Diversion of 0.05 Ha of Forest Land for Laying Underground Irrigation Water… — more information requested, 8.1 km away
- Diversion of 0.0165 Ha. of Forest Land for Laying Underground Irrigation Water… — lapsed, 8.1 km away
- Diversion of 0.0165 ha. of Forest Land for laying Underground irrigation water… — more information requested, 8.1 km away
- Tambekhani (Mal) Stone Quarry, Area- 3.00 Ha out of 4.04 Ha, Kh. No.- 57/1,… — environmental approval granted, 8.6 km away
- Ideal Energy Projects Limited (Expansion of Existing Thermal Power Plant) — environmental approval granted, 8.9 km away
- Ideal Energy Projects Limited (Expansion of Existing Thermal Power Plant) — cleared for impact study, 8.9 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.