Project details
| Status | In-principle approval, conditions pending |
|---|---|
| Status since | 1 May 2025 |
| Application filed | 26 Feb 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Power |
| Applicant | M/S. Adani Electricity Mumbai Infra LTD. (Aemil) |
| Land area | 43,900.6 acres (17,766 ha) |
| Forest land | 55.1 acres (22.3 ha) |
| Project cost | ₹2,165.2 crore |
| Village / locality | Navasai |
| Taluk / tehsil | Vasai |
| District | Palghar |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-15203 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 26 Feb 2024 (this page) | In-principle approval, conditions pending | 43,900.6 acres | ₹2,165.2 crore |
| New project filed 22 Feb 2024 | More information requested | 43,900.6 acres | ₹2,165.2 crore |
In context
23 applications in Palghar since January 2022 are in the same category (Power): 5 approved, 13 filed or under review, and 5 withdrawn, lapsed or rejected. At 43,900.6 acres, this one is larger than 91% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Navasai, Vasai, Palghar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 1000 MW + 320 KV HVDC VSC based Link between 400 KV MSETCL Kudus EHV… — more information requested, 0 m away
- For Seeking Prior Approval for Exploration for Geotechnical Investigation by… — forest land use approved, 3.9 km away
- Shri. Prakash Achyut Samant, Shri. Ravindra Achyut Samant & Shri. Rajendra… — environmental approval granted, 6.1 km away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 6.2 km away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 6.2 km away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 6.2 km away
- Basalt stone quarry of Shri. Prakash Achyut Samant, Shri. Ravindra Achyut… — under environmental review, 6.3 km away
- Diversion of 0.0985 Ha. Reserved Forest Land for "laying the Proposed Railway… — more information requested, 6.6 km away
All 3 Adani Electricity Mumbai projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.