One of 2 filings for this project. The project's main page, with every filing and where each stands: 1000 MW + 320 KV HVDC VSC based Link between 400 KV MSETCL Kudus EHV Substation and…
Project details
| Status | More information requested |
|---|---|
| Status since | 22 Feb 2024 |
| Application filed | 22 Feb 2024 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Power |
| Applicant | M/S. Adani Electricity Mumbai Infra LTD. (Aemil) |
| Land area | 43,900.6 acres (17,766 ha) |
| Project cost | ₹2,165.2 crore |
| Village / locality | Navasai |
| Taluk / tehsil | Vasai |
| District | Palghar |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-16522 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 26 Feb 2024 | In-principle approval, conditions pending | 43,900.6 acres | ₹2,165.2 crore |
| New project filed 22 Feb 2024 (this page) | More information requested | 43,900.6 acres | ₹2,165.2 crore |
In context
23 applications in Palghar since January 2022 are in the same category (Power): 5 approved, 13 filed or under review, and 5 withdrawn, lapsed or rejected. At 43,900.6 acres, this one is larger than 91% of them.
1 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Navasai, Vasai, Palghar, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- 1000 MW + 320 KV HVDC VSC based Link between 400 KV MSETCL Kudus EHV… — in-principle approval, conditions pending, 0 m away
- For Seeking Prior Approval for Exploration for Geotechnical Investigation by… — forest land use approved, 3.9 km away
- Shri. Prakash Achyut Samant, Shri. Ravindra Achyut Samant & Shri. Rajendra… — environmental approval granted, 6.1 km away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 6.2 km away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 6.2 km away
- Proposed School Building of M/s Vidya Vikas education Trust's Universal… — environmental approval granted, 6.2 km away
- Basalt stone quarry of Shri. Prakash Achyut Samant, Shri. Ravindra Achyut… — under environmental review, 6.3 km away
- Diversion of 0.0985 Ha. Reserved Forest Land for "laying the Proposed Railway… — more information requested, 6.6 km away