What is this project?
Diversion of 79.9793 ha forest land for Warasgaon-Warangi Pumped Storage Project (1500 MW) is a proposed water and irrigation project in Vagheri, Mahad, Raigarh, Maharashtra. The site covers 30,994.8 acres.
Who is building it?
The applicant is Adani Hydro Energy Three Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Under forest review”, as of 27 Nov 2026.
Where is it?
In Vagheri, Mahad, Raigarh, Maharashtra.
How big is it?
It has a stated cost of ₹55.2 crore; a site of 30,994.8 acres and 197.6 acres (80 ha) of forest land.
When was it filed?
The application was filed on 13 Jul 2026.
Project details
| Official title | Diversion of 79.9793 ha forest land for Warasgaon-Warangi Pumped Storage Project (1500 MW) located at Village Khole and Warangi, Taluka Velhe and Mahad, Districts Pune and Raigad, Maharashtra, by M/s. Adani Hydro Energy Three Limited under the Van (Sanrakshan Evam Samvardhan) Adhiniyam, 1980. |
|---|---|
| Status | Under forest review |
| Status since | 20 Jul 2026 |
| Application filed | 13 Jul 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Water & irrigation |
| Applicant | Adani Hydro Energy Three Limited |
| Land area | 30,994.8 acres (12,543.2 ha) |
| Forest land | 197.6 acres (80 ha) |
| Project cost | ₹55.2 crore |
| Village / locality | Vagheri |
| Taluk / tehsil | Mahad |
| District | Raigarh |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-15808 |
In context
31 applications in Raigarh since January 2022 are in the same category (Water & irrigation): 11 approved, 14 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 30,994.8 acres, this one is larger than 97% of them.
2 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Vagheri, Mahad, Raigarh, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Pane Pumped Storage Project with the capacity of 1500 MW at Villages:… — lapsed, 3.7 km away
- Proposed Pane Pumped Storage Project with the capacity of 1500 MW at Villages:… — cleared for impact study, 4.2 km away
- Kumbhe Pumped Storage Project (1100 MW) — lapsed, 9.9 km away
- Kumbhe Pumped Storage Project (1100 MW) — cleared for impact study, 9.9 km away
- Setting up Steel Plant with processes of Pickling, Cold Rolling, Galvanizing &… — more information requested, 15.4 km away
- No Increase Pollution Load (NIPL) for Product Mix of Plant Capacity 25,50,000… — initial checks, 16.6 km away
- Industrial project by M/s. POSCO Maharashtra Steel Pvt. Ltd. (PMSPL). — initial checks, 16.6 km away
- Amalgamation of Existing Environmental Clearance of CGL, CRM and ACL… — environmental approval granted, 16.6 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.