What is Tarali Pumping Storage Project (1500 MW)?
Tarali Pumping Storage Project (1500 MW) is a withdrawn project in Kalambe, Patan, Satara, Maharashtra. The site covers 372.5 acres.
Who is building it?
The applicant is Adani Green Energy Limited.
Has it been approved?
No. The application was withdrawn on 1 Mar 2024, so it is no longer under consideration.
Where is it?
In Kalambe, Patan, Satara, Maharashtra.
How big is it?
It has a stated cost of ₹5,675 crore and a site of 372.5 acres.
When was it filed?
The application was filed on 1 Mar 2024.
One of 2 filings for this project. The project's main page, with every filing and where each stands: Tarali Pumping Storage Project (1500 MW)
Project details
| Status | Withdrawn |
|---|---|
| Status since | 1 Mar 2024 |
| Application filed | 1 Mar 2024 |
| Approval sought | Wildlife review |
| Application type | New project |
| Sector | Other |
| Applicant | Adani Green Energy Limited |
| Land area | 372.5 acres (150.7 ha) |
| Project cost | ₹5,675 crore |
| Village / locality | Kalambe |
| Taluk / tehsil | Patan |
| District | Satara |
| State | Maharashtra |
| Location from | Site boundary on record |
| Our reference | WID-MH-16535 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 13 Jan 2025 | Under wildlife review | 372.5 acres | ₹56.8 crore |
| New project filed 1 Mar 2024 (this page) | Withdrawn | 372.5 acres | ₹5,675 crore |
In context
7 applications in Satara since January 2022 are in the same category (Other): 0 approved, 5 filed or under review, and 2 withdrawn, lapsed or rejected.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Kalambe, Patan, Satara, Maharashtra. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Tarali Pumping Storage Project (1500 MW) — environmental approval granted, 0 m away
- Tarali Pumping Storage Project (1500 MW) — environmental approval granted, 0 m away
- Tarali Pumping Storage Project (1500 MW) — cleared for impact study, 0 m away
- Tarali Pumped Storage Project with a capacity of 1500MW in Patan Taluka,… — withdrawn, 50 m away
- Proposed Tarali Pumped Storage Project (1500 MW), covering an area of 150.7400… — under wildlife review, 500 m away
- Tarali Pumping Storage Project (1500 MW) — under wildlife review, 500 m away
- Re-Diversion of Forest Land — more information requested, 2.2 km away
- Nivakane (Integrated) Pumped Storage Project — environmental approval granted, 4.2 km away
More from Adani Green Energy Limited in Satara
- Proposed Tarali Pumped Storage Project (1500 MW), covering an area of 150.7400… — under wildlife review
- Nivakane (Integrated) Pumped Storage Project — more information requested
- Nivakane (Integrated) Pumped Storage Project — environmental approval granted
- Nivakane Pumped Storage Project — more information requested
- Nivakane (Integrated) Pumped Storage Project — cleared for impact study
- Tarali Pumping Storage Project (1500 MW) — environmental approval granted
13 Adani Green Energy projects in Satara
All 39 Adani Green Energy projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.