Quick answers
What is this project?
"Surve Larung Lumshnong Limestone Deposit (44.58 Ha.)'' with a proposed maximum excavation 1366475.2 TPA (654577 TPA of limestone and 711898.2 TPA of waste including topsoil) by M/s. Green Valliey Industries Limited is a proposed mining project in Lum Shnong, Khliehriat, East Jaintia Hills, Meghalaya. The site covers 110.2 acres.
Who is building it?
The applicant is Green Valliey Industries Limited.
Has it been approved?
Yes. Its status is “Cleared for impact study” (since 24 Feb 2025), as of 27 Nov 2026.
Where is it?
In Lum Shnong, Khliehriat, East Jaintia Hills, Meghalaya.
How big is it?
It has a stated cost of ₹30.1 crore and a site of 110.2 acres.
When was it filed?
The application was filed on 1 Apr 2024.
Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 24 Feb 2025 |
| Application filed | 1 Apr 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Green Valliey Industries Limited |
| Land area | 110.2 acres (44.6 ha) |
| Project cost | ₹30.1 crore |
| Village / locality | Lum Shnong |
| Taluk / tehsil | Khliehriat |
| District | East Jaintia Hills |
| State | Meghalaya |
| Location from | Site boundary on record |
| Our reference | WID-ML-00076 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 3 Aug 2026 | Under environmental review | 110.2 acres | ₹30.1 crore |
| Early planning filed 1 Apr 2024 (this page) | Cleared for impact study | 110.2 acres | ₹30.1 crore |
In context
65 applications in East Jaintia Hills since January 2022 are in the same category (Mining): 49 approved, 11 filed or under review, and 5 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 110.2 acres, this one is larger than 75% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 115.1 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 29 mining leases have applied within 5 km.
Where it is
Lum Shnong, Khliehriat, East Jaintia Hills, Meghalaya. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- "Surve Larung Lumshnong Limestone Deposit (44.58 Ha.)'' with a proposed… — under environmental review, 0 m away
- Forest Diversion Proposal of Surve Larung Lumshnong Limestone Deposit over an… — under forest review, 0 m away
- Larung Limestone Mine — cleared for impact study, 450 m away
- Larung Limestone Mine over an area of 4.76 Ha of M/s. JUD Cements Limited — returned to applicant, 750 m away
- 43 MW imported coal based Thermal Power Plant project at Lumshnong, East… — withdrawn, 1.1 km away
- 8 MW Thermal Power Plant at Lumshnong, East Jaintia Hills District, Meghalaya — environmental approval granted, 1.1 km away
- 100% Coal-based 8 MW Thermal Power Plant project at Lumshnong, East Jaintia… — withdrawn, 1.1 km away
- 43 MW Thermal Power Plant at Lumshnong, East Jaintia Hills District, Meghalaya — environmental approval granted, 1.1 km away
More from Green Valliey Industries Limited in East Jaintia Hills
- Madan Pyrda (Block-1) by M/s. Green Valliey Industries Limited — environmental approval granted
- Madan Pyrda (Block-1) by M/s. Green Valliey Industries Limited — environmental approval granted
- Madan Pyrda (Block- 2) Limestone Deposit — environmental approval granted
- Forest Diversion Proposal of Surve Larung Lumshnong Limestone Deposit over an… — under forest review
- GVIL Shale Mine — environmental approval granted
- GVIL Shale Mine — environmental approval granted
All 9 Green Valliey Industries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.