1x660 MW Satpura Super-critical Thermal Power Project (Expansion, Phase-V, Unit no. 12) at Sarni, Tehsil Ghoradongri, Village Brahmanwada Ryt, District Betul, Madhya Pradesh is an approved power project in Brahmanwada Ryt (Viran), Ghoda Dongri, Betul, Madhya Pradesh. The site covers 1,295.8 acres.
Who is building it?
The applicant is Madhya Pradesh Power Generating Co. Limited (Mppgcl).
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 21 Nov 2023), as of 27 Nov 2026.
Where is it?
In Brahmanwada Ryt (Viran), Ghoda Dongri, Betul, Madhya Pradesh.
How big is it?
It has a stated cost of ₹9,018.5 crore and a site of 1,295.8 acres.
When was it filed?
The application was filed on 21 Nov 2023.
Project details
| Status | Environmental approval granted |
|---|---|
| Status since | 21 Nov 2023 |
| Application filed | 21 Nov 2023 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Power |
| Applicant | Madhya Pradesh Power Generating Co. Limited (Mppgcl) |
| Land area | 1,295.8 acres (524.4 ha) |
| Project cost | ₹9,018.5 crore |
| Village / locality | Brahmanwada Ryt (Viran) |
| Taluk / tehsil | Ghoda Dongri |
| District | Betul |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-00170 |
In context
39 applications in Betul since January 2022 are in the same category (Power): 7 approved, 26 filed or under review, and 6 withdrawn, lapsed or rejected. The approved ones took a median of 11 months from filing to approval. At 1,295.8 acres, this one is larger than 95% of them.
15 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Brahmanwada Ryt (Viran), Ghoda Dongri, Betul, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- P2P Networks Private Limited - Laying of OFC cable between Sarni 220 KV Sub… — forest land use approved, 450 m away
- Development of Samudayik Kendra at Mokshdham — lapsed, 500 m away
- 2x250 MW Thermal Power Plant at Satpura Thermal Power Station (STPS), Sarni –… — environmental approval granted, 500 m away
- Amendment of lx660 MW Satpura Ultra Super-critical Thermal Power Project -… — under environmental review, 650 m away
- Amendment of lx660 MW Satpura Ultra Super-critical Thermal Power Project -… — environmental approval granted, 650 m away
- Expansion of 2x250 MW (Phase IV) & 1x660 MW (Phase V) -Proposed 2nd unit of… — returned to applicant, 850 m away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — forest land use approved, 1.3 km away
- 11 KV Satpuda-1 No. Interconnection Work under RDSS Scheme — more information requested, 1.4 km away
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.