What is Block-B Expansion OCP NCL?
Block-B Expansion OCP NCL is a lapsed mining project in Gorbi, Chitrangi, Singrauli, Madhya Pradesh. The site covers 4,341.1 acres.
Who is building it?
The applicant is Block-B Project Northern Coalfields Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2024, so it is no longer under consideration.
Where is it?
In Gorbi, Chitrangi, Singrauli, Madhya Pradesh.
How big is it?
It has a stated cost of ₹1,549 crore and a site of 4,341.1 acres.
When was it filed?
The application was filed on 14 Jun 2023.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2024 |
| Application filed | 14 Jun 2023 |
| Approval sought | Environmental approval |
| Application type | Amendment |
| Sector | Mining |
| Applicant | Block-B Project Northern Coalfields Limited |
| Land area | 4,341.1 acres (1,756.8 ha) |
| Project cost | ₹1,549 crore |
| Village / locality | Gorbi |
| Taluk / tehsil | Chitrangi |
| District | Singrauli |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-02125 |
In context
268 applications in Singrauli since January 2022 are in the same category (Mining): 152 approved, 40 filed or under review, and 76 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 4,341.1 acres, this one is larger than 90% of them.
2 other mining leases have applied within 500 m of this site; together with this one they cover 11,757.6 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 3 mining leases have applied within 5 km.
Where it is
Gorbi, Chitrangi, Singrauli, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Block-B Expansion OCP Project — environmental approval granted, 50 m away
- Block-B Expansion OCP Project — environmental approval granted, 50 m away
- Block-B Expansion OCP Project — cleared for impact study, 50 m away
- Block-B Expansion Project — forest land use approved, 50 m away
- Block-B Expansion OCP NCL — lapsed, 150 m away
- Jio Digital Fiber Pvt. Ltd. Linear Ofc 5g Project In Row Corridor Of Principal… — forest land use approved, 3.1 km away
- Proposed 2.48 MTPA Coal Washery Project by Mahavir Coal Resources Private… — cleared for impact study, 3.2 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — lapsed, 3.4 km away
More from Block-B Project Northern Coalfields Limited in Singrauli
- Block-B Expansion OCP Project — environmental approval granted
- Block-B Expansion OCP Project — environmental approval granted
- Block-B Expansion OCP Project — cleared for impact study
- Block-B Expansion Project — forest land use approved
- Block-B Expansion OCP NCL — lapsed
All 6 Block-B Project Northern projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.