What is Bhamrah Sand Quarry?
Bhamrah Sand Quarry is a proposed mining project in Bhamaraha, Manpur, Umaria, Madhya Pradesh. The site covers 15.1 acres.
Who is building it?
The applicant is Gayaprasad Anjne.
Has it been approved?
Not yet. The application is still under review: its status is “Under environmental review”, as of 27 Nov 2026.
Where is it?
In Bhamaraha, Manpur, Umaria, Madhya Pradesh.
How big is it?
It has a stated cost of ₹95 lakh and a site of 15.1 acres.
When was it filed?
The application was filed on 26 Jan 2024.
One of 3 filings for this project. The project's main page, with every filing and where each stands: Bhamrah Sand Quarry
Project details
| Status | Under environmental review |
|---|---|
| Status since | 26 Jan 2024 |
| Application filed | 26 Jan 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Mining |
| Applicant | Gayaprasad Anjne |
| Land area | 15.1 acres (6.1 ha) |
| Project cost | ₹95 lakh |
| Village / locality | Bhamaraha |
| Taluk / tehsil | Manpur |
| District | Umaria |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-04011 |
All filings for this project
This project has 3 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| New project filed 2 Jun 2024 | Lapsed | 15.1 acres | ₹95 lakh |
| Early planning filed 29 Jan 2024 | Cleared for impact study | 27.8 acres | ₹95 lakh |
| Early planning filed 26 Jan 2024 (this page) | Under environmental review | 15.1 acres | ₹95 lakh |
In context
145 applications in Umaria since January 2022 are in the same category (Mining): 65 approved, 21 filed or under review, and 59 withdrawn, lapsed or rejected. The approved ones took a median of 3 months from filing to approval. At 15.1 acres, this one is larger than 60% of them.
No other mining lease on record has applied within 5 km of this site.
Where it is
Bhamaraha, Manpur, Umaria, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Bhamrah Sand Quarry — cleared for impact study, 50 m away
- Bhamrah Sand Quarry — lapsed, 50 m away
- Work of New 33 KV Line Interconnection From 220/33 KV Ss Bijauri to 33/11 KV… — lapsed, 6.3 km away
- 33 KV Feeder From 220/33 KV Bijauri to Devri Line — under wildlife review, 6.6 km away
- 33 KV Feeder From 220/33 KV Bijauri to Devri Line — application filed, 6.6 km away
- 33 KV Feeder From 220/33 KV Bijauri to Devri Line — under forest review, 6.6 km away
- Govarde Badar Sand Mine — environmental approval granted, 7.3 km away
- Work of New 33 KV Line Interconnection From 220/33 KV Ss Bijauri to 33/11 KV… — lapsed, 8 km away
More from Gayaprasad Anjne in Umaria
- Amiliya Sand Quarry_11.00 ha — withdrawn
- Amiliya Sand Quarry_9.00 ha — withdrawn
- Parasi Sand Quarry — withdrawn
- Mohbala Sand Quarry — environmental approval granted
- Khairbhar-1 River Sand Quarry — environmental approval granted
- Jhala River Sand Quarry — environmental approval granted
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.