Quick answers
What is this project?
200 KLPD Grain Based Distillery Plant with Product of RS/ENA with Bottling Plant/Fuel Ethanol Plant and Pharma grade Ethanol with Cogeneration Power Plant of 7.0 MW is a lapsed industrial project in Basi, Waraseoni, Balaghat, Madhya Pradesh. The site covers 16.1 acres.
Who is building it?
The applicant is Jakson Biofuels Private Limited.
Has it been approved?
No. The application was lapsed on 29 Oct 2025, so it is no longer under consideration.
Where is it?
In Basi, Waraseoni, Balaghat, Madhya Pradesh.
How big is it?
It has a stated cost of ₹350 crore and a site of 16.1 acres.
When was it filed?
The application was filed on 25 Jul 2025.
Project details
| Status | Lapsed |
|---|---|
| Status since | 29 Oct 2025 |
| Application filed | 25 Jul 2025 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Jakson Biofuels Private Limited |
| Land area | 16.1 acres (6.5 ha) |
| Project cost | ₹350 crore |
| Village / locality | Basi |
| Taluk / tehsil | Waraseoni |
| District | Balaghat |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-07146 |
In context
10 applications in Balaghat since January 2022 are in the same category (Industry): 4 approved, 2 filed or under review, and 4 withdrawn, lapsed or rejected. At 16.1 acres, this one is smaller than 60% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Basi, Waraseoni, Balaghat, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Grain Base Fuel Ethanol Unit of 150 Klpd to 200 Klpd and 4 MW… — initial checks, 250 m away
- Transfer of Environment Clearance (EC) granted by MoEF&CC, New Delhi Vide EC… — under environmental review, 250 m away
- Jio Digital Fiber Pvt. Ltd. Linear Ofc 5g Project In Row Corridor Of Principal… — lapsed, 1.4 km away
- Basi Sand Quarry — environmental approval granted, 1.9 km away
- Ansera Stione Quarry — withdrawn, 2.8 km away
- Ansera Crusher Stone Quarry — environmental approval granted, 2.8 km away
- Capacity Expansion of Grain Based Fuel Ethanol Unit from 195 KLD to 345 KLD — lapsed, 3.9 km away
- Gattapayli Sand Quarry — environmental approval granted, 4.6 km away
More from Jakson Biofuels Private Limited in Balaghat
- Expansion of Grain Base Fuel Ethanol Unit of 150 Klpd to 200 Klpd and 4 MW… — initial checks
- Transfer of Environment Clearance (EC) granted by MoEF&CC, New Delhi Vide EC… — under environmental review
All 3 Jakson Biofuels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.