Expansion of Grain Base Fuel Ethanol Unit of 150 Klpd to 200 Klpd and 4 MW Co-Generation Power Plant is a proposed power project in Basi, Waraseoni, Balaghat, Madhya Pradesh. The site covers 26.8 acres.
Who is building it?
The applicant is Jakson Biofuels Private Limited.
Has it been approved?
Not yet. The application is still under review: its status is “Initial checks”, as of 27 Nov 2026.
Where is it?
In Basi, Waraseoni, Balaghat, Madhya Pradesh.
How big is it?
It has a stated cost of ₹5 crore and a site of 26.8 acres.
When was it filed?
The application was filed on 30 May 2026.
Project details
| Status | Initial checks |
|---|---|
| Status since | 30 May 2026 |
| Application filed | 30 May 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Power |
| Applicant | Jakson Biofuels Private Limited |
| Land area | 26.8 acres (10.8 ha) |
| Project cost | ₹5 crore |
| Village / locality | Basi |
| Taluk / tehsil | Waraseoni |
| District | Balaghat |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-09052 |
In context
45 applications in Balaghat since January 2022 are in the same category (Power): 1 approved, 18 filed or under review, and 26 withdrawn, lapsed or rejected. At 26.8 acres, this one is smaller than 90% of them.
10 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Basi, Waraseoni, Balaghat, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Transfer of Environment Clearance (EC) granted by MoEF&CC, New Delhi Vide EC… — under environmental review, 0 m away
- 200 KLPD Grain Based Distillery Plant with Product of RS/ENA with Bottling… — lapsed, 250 m away
- Basi Sand Quarry — environmental approval granted, 1.6 km away
- Jio Digital Fiber Pvt. Ltd. Linear Ofc 5g Project In Row Corridor Of Principal… — lapsed, 1.7 km away
- Ansera Stione Quarry — withdrawn, 2.5 km away
- Ansera Crusher Stone Quarry — environmental approval granted, 2.6 km away
- Capacity Expansion of Grain Based Fuel Ethanol Unit from 195 KLD to 345 KLD — lapsed, 4.1 km away
- Gattapayli Sand Quarry — environmental approval granted, 4.3 km away
More from Jakson Biofuels Private Limited in Balaghat
- 200 KLPD Grain Based Distillery Plant with Product of RS/ENA with Bottling… — lapsed
- Transfer of Environment Clearance (EC) granted by MoEF&CC, New Delhi Vide EC… — under environmental review
All 3 Jakson Biofuels projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.