Quick answers
What is this project?
Electrification of Pvtg Habitation Baigan Tola of Village- Badhar (Census Code 501929) is a lapsed building project in Audhera, Anuppur, Madhya Pradesh. The site covers 1.1 acres.
Who is building it?
The applicant is Rural Development.
Has it been approved?
No. The application was lapsed on 5 Nov 2024, so it is no longer under consideration.
Where is it?
In Audhera, Anuppur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹7 lakh; a site of 1.1 acres and 1,500 m² of forest land.
When was it filed?
The application was filed on 6 Feb 2024.
Project details
| Status | Lapsed |
|---|---|
| Status since | 5 Nov 2024 |
| Application filed | 6 Feb 2024 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Buildings & townships |
| Applicant | Rural Development |
| Land area | 1.1 acres (0.5 ha) |
| Forest land | 1,500 m² |
| Project cost | ₹7 lakh |
| Village / locality | Audhera |
| Taluk / tehsil | Anuppur |
| District | Anuppur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-11008 |
In context
20 applications in Anuppur since January 2022 are in the same category (Buildings & townships): 1 approved, 2 filed or under review, and 17 withdrawn, lapsed or rejected. At 1.1 acres, this one is smaller than 80% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Audhera, Anuppur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Naugai Quarry Lease — lapsed, 3.2 km away
- Naugawan Stone Quarry — lapsed, 5 km away
- Naugawan Stone Quarry — lapsed, 5 km away
- Bhamraha Stone Mine For Making Boulder & Gitti — environmental approval granted, 5.4 km away
- Badhar Quarry (Basalt Stone) Lease — environmental approval granted, 6.6 km away
- Badhar Stone Quarry — lapsed, 6.6 km away
- Badhar Stone Quarry — lapsed, 6.6 km away
- Jio Digital Fiber Pvt Ltd Linear OFC 5G Project in ROW Corridor of Principal… — lapsed, 7.8 km away
More from Rural Development in Anuppur
- Bifurcation of 33 KV Kotma old feeder from 132 KV EHV S/S to 33/11 KV S/S… — lapsed
- Work of 33 KV Line for New 33/11 KV Substation — forest land use approved
- Bifurcation of 33 KV Feeder from 132 KV EHV S/S to 33/11 KV S/S Funga — forest land use approved
- Electrification work of PVTG Habitation Village Akua, Census code-501932 — lapsed
- Stringing of additional 33 KV Line from 33/11 KV S/S Funga to Pasla Village — forest land use approved
- Electrification Work in Neelkanth Ashram at Village Miriya — lapsed
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.