Quick answers
What is this project?
Approach Road for Intake Water Pump House facility for proposed Anuppur Thermal Power Project is an approved road project in Paraur, Anuppur, Madhya Pradesh. The site covers 25 acres.
Who is building it?
The applicant is Adani Power Limited.
Has it been approved?
Yes. Its status is “Forest land use approved” (since 16 Sept 2026), as of 27 Nov 2026.
Where is it?
In Paraur, Anuppur, Madhya Pradesh.
How big is it?
It has a stated cost of ₹4.3 crore; a site of 25 acres and 1.9 acres (0.8 ha) of forest land.
When was it filed?
The application was filed on 6 Jan 2026.
Project details
| Official title | Construction of Approach Road for Intake Water Pump House facility for proposed Anuppur Thermal Power Project at District Anuppur, Madhya Pradesh |
|---|---|
| Status | Forest land use approved |
| Status since | 16 Sept 2026 |
| Application filed | 6 Jan 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Roads & highways |
| Applicant | Adani Power Limited |
| Land area | 25 acres (10.1 ha) |
| Forest land | 1.9 acres (0.8 ha) |
| Project cost | ₹4.3 crore |
| Village / locality | Paraur |
| Taluk / tehsil | Anuppur |
| District | Anuppur |
| State | Madhya Pradesh |
| Location from | Site boundary on record |
| Our reference | WID-MP-11107 |
In context
39 applications in Anuppur since January 2022 are in the same category (Roads & highways): 8 approved, 18 filed or under review, and 13 withdrawn, lapsed or rejected. The approved ones took a median of 5 months from filing to approval. At 25 acres, this one is larger than 94% of them.
3 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Paraur, Anuppur, Madhya Pradesh. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Proposed Railway corridor for Newzone India Private Limited near Dhurwasin… — initial checks, 4.7 km away
- Cholna Sand Mine — lapsed, 4.9 km away
- Cholna Sand Mine — cleared for impact study, 4.9 km away
- Cholna Granite Deposit Quarry of M/s Kisan Exports — environmental approval granted, 5.8 km away
- Dekhal Sand Mine — environmental approval granted, 6.3 km away
- New Zone Thermal Power Plant, Anuppur, 2x800 MW Coal Based Ultra Super… — environmental approval granted, 6.3 km away
- New Zone Thermal Power Plant, Anuppur, 2x800 MW Coal Based Ultra Super… — environmental approval granted, 6.3 km away
- New Zone Thermal Power Plant, Anuppur, 2x800 MW Coal Based Ultra Super… — cleared for impact study, 6.3 km away
More from Adani Power Limited in Anuppur
- Residential Township of Anuppur Thermal Power Plant — under environmental review
- Water Intake Facilities including underground Water Pipeline, Anicuts and… — under forest review
- Proposed Railway Siding From Baihatola Station to Anuppur TPP Project site by… — under forest review
- Proposed 4x800 MW Coal Based Ultra Super Critical Thermal Power Plant (USCTPP)… — environmental approval granted
- Proposed 4x800 MW Coal Based Ultra Super Critical Thermal Power Plant (USCTPP)… — cleared for impact study
6 Adani Power projects in Anuppur
All 68 Adani Power projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.