Project details
| Status | Cleared for impact study |
|---|---|
| Status since | 28 Aug 2024 |
| Application filed | 4 May 2024 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | UltraTech Cement Limited |
| Land area | 89.9 acres (36.4 ha) |
| Project cost | ₹935 crore |
| Village / locality | Khamarnuagan |
| Taluk / tehsil | Khuntuni |
| District | Cuttack |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-00241 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Amendment filed 20 Mar 2025 | Cleared for impact study | 105.9 acres | ₹957 crore |
| Early planning filed 4 May 2024 (this page) | Cleared for impact study | 89.9 acres | ₹935 crore |
In context
14 applications in Cuttack since January 2022 are in the same category (Industry): 8 approved, 2 filed or under review, and 4 withdrawn, lapsed or rejected. At 89.9 acres, this one is larger than 57% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Khamarnuagan, Khuntuni, Cuttack, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Cement Production Capacity (3.0 Million TPA to 6.0 Million TPA)… — cleared for impact study, 50 m away
- Industrial project by Karma Re-Rollers PVT LTD — more information requested, 2.5 km away
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 1,20,000 TPA to… — environmental approval granted, 4 km away
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 1,20,000 TPA to… — cleared for impact study, 4.1 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — cleared for impact study, 4.7 km away
- Transfer of Terms of Reference (Change in Name) subsequently to NCLT Order… — cleared for impact study, 4.8 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — more information requested, 4.8 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — cleared for impact study, 4.8 km away
All 182 UltraTech Cement projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.