One of 2 filings for this project. The project's main page, with every filing and where each stands: Expansion of Steel Plant – DRI Kilns (Sponge Iron from 1,20,000 TPA to 4,50,000 TPA),…
Project details
| Official title | Expansion of Steel Plant – DRI Kilns (Sponge Iron from 1,20,000 TPA to 4,50,000 TPA), Induction Furnaces along with CCM & LRF (Hot Billets / MS Ingots / Billets from 65,000 TPA to 3,96,000 TPA), Ferro Alloys - 1 x 9 MVA (FeCr - 6,250 TPA / FeMn- 9,000 TPA) to 3 x 9 MVA (FeCr- 45,000 TPA / SiMn- 43,200 TPA / FeMn-75,600 TPA / FeSi-21,000 TPA / Pig Iron- 75,600 TPA), WHRB (DRI) based Power Plant from 5 MW to 29 MW, AFBC based Power Plant from 14 MW to 44 MW, new WHRB (BF gases) – 5.0 MW, New Sinter Plant (4,27,680 TPA), New 8,00,000 TPA of Pellet Plant along with Producer Gasifier 24,000 NM3/Hr., New Briquetting Plant - 300 Kg/Hr. & New Brick Manufacturing unit (68,100 Bricks/day) by M/s Beekay Steel Industries Ltd., located at Village: Rampei, Tehsil: Athagarh, District: Cuttack, Odisha |
|---|---|
| Status | Cleared for impact study |
| Status since | 8 Mar 2023 |
| Application filed | 8 Mar 2023 |
| Approval sought | Environmental approval |
| Application type | Early planning |
| Sector | Industry |
| Applicant | Beekay Steel Industries Limited |
| Land area | 180.9 acres (73.2 ha) |
| Project cost | ₹1,785.6 crore |
| Village / locality | Rampei |
| Taluk / tehsil | Khuntuni |
| District | Cuttack |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-00472 |
All filings for this project
This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):
| Filing | Status | Land | Cost |
|---|---|---|---|
| Expansion filed 13 Jun 2024 | Environmental approval granted | 180.9 acres | ₹1,785.6 crore |
| Early planning filed 8 Mar 2023 (this page) | Cleared for impact study | 180.9 acres | ₹1,785.6 crore |
In context
14 applications in Cuttack since January 2022 are in the same category (Industry): 8 approved, 2 filed or under review, and 4 withdrawn, lapsed or rejected. At 180.9 acres, this one is larger than 71% of them.
11 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Rampei, Khuntuni, Cuttack, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Expansion of Steel Plant – DRI Kilns (Sponge Iron from 1,20,000 TPA to… — environmental approval granted, 50 m away
- 3x800 MW Nilanchal Ultra Super Critical Thermal Power Plant (USCTPP) by Orissa… — not approved, 2.2 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — cleared for impact study, 2.2 km away
- Transfer of Terms of Reference (Change in Name) subsequently to NCLT Order… — cleared for impact study, 2.2 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — more information requested, 2.2 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — cleared for impact study, 2.2 km away
- Proposed 3x800 MW Coal Based Ultra Super Critical Nilanchal Thermal Power… — not approved, 2.2 km away
- Expansion of Cement Production Capacity (3.0 Million TPA to 6.0 Million TPA)… — cleared for impact study, 4.1 km away
All 3 Beekay Steel Industries projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.