Returned to applicantIndustry · Sambalpur, Odisha

Environmental Clearance as per Provision under EIA Notification No. S.O. 3250 (E) dtd.20th July 2022 for Existing Rolling Mill with CCM having Installed Capacity of 3,00,000 TPA by Rolling Mill Division of M/s Viraj Steel & Energy Private Limited

Environmental Clearance as per Provision under EIA Notification No. S.O. 3250 (E) dtd.20th July 2022 for Existing Rolling Mill with CCM having Installed Capacity of 3,00,000 TPA by Rolling Mill Division of M/s Viraj Steel & Energy Private Limited is a proposed industrial project in Gurupali, Rengali, Sambalpur, Odisha. The site covers 12.2 acres. Its stated project cost is ₹54.1 crore. As of 27 Nov 2026, its status is “Returned to applicant” (since 15 Feb 2025).

See it on the live map All projects in Sambalpur

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

One of 2 filings for this project. The project's main page, with every filing and where each stands: Environmental Clearance as per Provision under EIA Notification No. S.O. 3250 (E)…

Project details

StatusReturned to applicant
Status since15 Feb 2025
Application filed4 Jul 2023
Approval soughtEnvironmental approval
Application typeNew project
SectorIndustry
ApplicantViraj Steel and Energy Private Limited
Land area12.2 acres (4.9 ha)
Project cost₹54.1 crore
Village / localityGurupali
Taluk / tehsilRengali
DistrictSambalpur
StateOdisha
Location fromSite boundary on record
Our referenceWID-OR-00590

All filings for this project

This project has 2 applications on record. Each is a separate step (an impact study, an approval, an expansion…):

FilingStatusLandCost
New project filed 27 Jul 2023Returned to applicant12.2 acres₹54.1 crore
New project filed 4 Jul 2023 (this page)Returned to applicant12.2 acres₹54.1 crore

In context

38 applications in Sambalpur since January 2022 are in the same category (Industry): 17 approved, 13 filed or under review, and 8 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 12.2 acres, this one is smaller than 79% of them.

24 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

Gurupali, Rengali, Sambalpur, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.