What is Developing? Open the mapMap

Returned to applicantPower · Jharsuguda, Odisha

Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 & 6) as Stage-III

Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 & 6) as Stage-III is a proposed power project in B>Rg>D, Lakhanpur, Jharsuguda, Odisha. The site covers 2,377.1 acres. Its stated project cost is ₹25,020.4 crore. As of 27 Nov 2026, its status is “Returned to applicant” (since 6 Nov 2025).

See it on the live map All projects in Jharsuguda

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Quick answers

What is this project?

Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 & 6) as Stage-III is a proposed power project in B>Rg>D, Lakhanpur, Jharsuguda, Odisha. The site covers 2,377.1 acres.

Who is building it?

The applicant is Odisha Power Generation Corporation Limited.

Has it been approved?

Not yet. The application is still under review: its status is “Returned to applicant”, as of 27 Nov 2026.

Where is it?

In B>Rg>D, Lakhanpur, Jharsuguda, Odisha.

How big is it?

It has a stated cost of ₹25,020.4 crore and a site of 2,377.1 acres.

When was it filed?

The application was filed on 14 Oct 2025.

Project details

Official titleExpansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 & 6) as Stage-III at Banaharpalli village, Jharsuguda district, Odisha state by M/s. Odisha Power Generation Corporation Ltd.
StatusReturned to applicant
Status since6 Nov 2025
Application filed14 Oct 2025
Approval soughtEnvironmental approval
Application typeAmendment
SectorPower
ApplicantOdisha Power Generation Corporation Limited
Land area2,377.1 acres (962 ha)
Project cost₹25,020.4 crore
Village / localityB>Rg>D
Taluk / tehsilLakhanpur
DistrictJharsuguda
StateOdisha
Location fromSite boundary on record
Our referenceWID-OR-02787

In context

19 applications in Jharsuguda since January 2022 are in the same category (Power): 8 approved, 8 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 2,377.1 acres, this one is larger than 89% of them.

9 other applications of any kind have been filed within 5 km of this site since January 2022.

Where it is

B>Rg>D, Lakhanpur, Jharsuguda, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Close to Talabira II & III: A 23-Million-Tonne-a-Year Coal Mine for Jharsuguda and Sambalpur, Odisha (11.8 km away).

Other projects nearby

More from Odisha Power Generation Corporation Limited in Jharsuguda