Quick answers
What is this project?
Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 & 6) as Stage-III is an approved power project in Barap>Li, Banaharapali, Jharsuguda, Odisha. The site covers 2,083.6 acres.
Who is building it?
The applicant is Odisha Power Generation Corporation Limited.
Has it been approved?
Yes. Its status is “Environmental approval granted” (since 4 Jun 2026), as of 27 Nov 2026.
Where is it?
In Barap>Li, Banaharapali, Jharsuguda, Odisha.
How big is it?
It has a stated cost of ₹25,020.4 crore and a site of 2,083.6 acres.
When was it filed?
The application was filed on 19 May 2026.
Project details
| Official title | Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 & 6) as Stage-III at Banaharpalli village, Jharsuguda district, Odisha state by M/s. Odisha Power Generation Corporation Ltd. |
|---|---|
| Status | Environmental approval granted |
| Status since | 4 Jun 2026 |
| Application filed | 19 May 2026 |
| Approval sought | Environmental approval |
| Application type | New project |
| Sector | Power |
| Applicant | Odisha Power Generation Corporation Limited |
| Land area | 2,083.6 acres (843.2 ha) |
| Project cost | ₹25,020.4 crore |
| Village / locality | Barap>Li |
| Taluk / tehsil | Banaharapali |
| District | Jharsuguda |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-03557 |
In context
19 applications in Jharsuguda since January 2022 are in the same category (Power): 8 approved, 8 filed or under review, and 3 withdrawn, lapsed or rejected. The approved ones took a median of 2 months from filing to approval. At 2,083.6 acres, this one is larger than 79% of them.
9 other applications of any kind have been filed within 5 km of this site since January 2022.
Where it is
Barap>Li, Banaharapali, Jharsuguda, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Close to Talabira II & III: A 23-Million-Tonne-a-Year Coal Mine for Jharsuguda and Sambalpur, Odisha (11.8 km away).
Other projects nearby
- Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 &… — cleared for impact study, 0 m away
- Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 &… — returned to applicant, 0 m away
- Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 &… — cleared for impact study, 550 m away
- JSW Steel Ltd. Coal Washery project (Ind Barath Energy (Utkal) Ltd.) — returned to applicant, 4.1 km away
- 400 KV D/C Transmission line connecting from 2x 350MW Thernal power plant to… — more information requested, 4.3 km away
- Expansion of Coal Based Thermal Power Plant from 1x350 MW to 2X350 MW" — environmental approval granted, 4.3 km away
- Transfer of Ownership from M/s Ind- Barath Energy (Utkal) Limited to M/s JSW… — lapsed, 4.3 km away
- Expansion of Coal Based Thermal Power Plant from 1x350 MW to 2X350 MW" — cleared for impact study, 4.3 km away
More from Odisha Power Generation Corporation Limited in Jharsuguda
- Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 &… — cleared for impact study
- Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 &… — returned to applicant
- Expansion of Coal Based Thermal Power Plant by addition of 2x660 MW (Unit 5 &… — cleared for impact study
All 4 Odisha Power Generation Corporation projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.