Quick answers
What is this project?
Diversion Over 16.574 Ha of Forest Land As Per Sabik Records (As on 25.10.1980) Within the Mining Lease Area of Joda East Iron Mine is a proposed mining project in Joda, Kendujhar, Odisha. The site covers 1,745.4 acres.
Who is building it?
The applicant is Tata Steel Limited.
Has it been approved?
Not yet. The application is still under review: its status is “More information requested”, as of 27 Nov 2026.
Where is it?
In Joda, Kendujhar, Odisha.
How big is it?
It has a stated cost of ₹1,300 crore; a site of 1,745.4 acres and 41 acres (16.6 ha) of forest land.
When was it filed?
The application was filed on 18 Aug 2026.
Project details
| Status | More information requested |
|---|---|
| Status since | 10 Sept 2026 |
| Application filed | 18 Aug 2026 |
| Approval sought | Forest land use |
| Application type | New project |
| Sector | Mining |
| Applicant | Tata Steel Limited |
| Land area | 1,745.4 acres (706.3 ha) |
| Forest land | 41 acres (16.6 ha) |
| Project cost | ₹1,300 crore |
| Village / locality | Joda |
| Taluk / tehsil | Joda |
| District | Kendujhar |
| State | Odisha |
| Location from | Site boundary on record |
| Our reference | WID-OR-04206 |
In context
213 applications in Kendujhar since January 2022 are in the same category (Mining): 110 approved, 46 filed or under review, and 57 withdrawn, lapsed or rejected. The approved ones took a median of 4 months from filing to approval. At 1,745.4 acres, this one is larger than 88% of them.
1 other mining lease has applied within 500 m of this site; together with this one they cover 3,403.7 acres. Under India's environmental rules, mining leases less than 500 m apart are assessed together as one cluster, so the combined area can decide which clearance is needed. 5 mining leases have applied within 5 km.
Where it is
Joda, Kendujhar, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.
Other projects nearby
- Amendment in Environmental Clearance granted to Joda East Iron Mine of Tata… — under environmental review, 50 m away
- Expansion of Iron Ore Production Capacity From 0.5716 Mtpa to 4.99 Mtpa at the… — cleared for impact study, 1 km away
- Expansion of Iron Ore Production Capacity From 0.5716 Mtpa to 4.99 Mtpa at the… — environmental approval granted, 1.1 km away
- Diversion Proposal for Seeking Prior Approval Under Section 2 of Van… — not approved, 3.6 km away
- Ratification of existing EC from EIA, 1994 to 2006 regime and Production… — under environmental review, 3.6 km away
- Enhancement in production capacity of Manganese Ore from 0.832 LTPA (0.978… — under environmental review, 3.9 km away
- Enhancement in production capacity of Manganese Ore from 0.832 LTPA (0.978… — under environmental review, 3.9 km away
- Laying of Water Pipeline from Village Kandra to Tanto for 2.4 MTPA Pallet… — lapsed, 4.2 km away
More from Tata Steel Limited in Kendujhar
- Amendment in Environmental Clearance granted to Joda East Iron Mine of Tata… — under environmental review
- Enhancement in production capacity of Manganese Ore from 0.832 LTPA (0.978… — under environmental review
- Enhancement in production capacity of Manganese Ore from 0.832 LTPA (0.978… — under environmental review
- Ratification of existing EC from EIA, 1994 to 2006 regime and Production… — under environmental review
- Diversion of Balance Forest Land Over 422.048 Ha Including Safety Zone Over… — lapsed
- Proposed Environment Clearance for Residential Project at Mouza – Bileipada,… — lapsed
27 Tata Steel projects in Kendujhar
All 104 Tata Steel projects across India
About this information
This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.