Not approvedPipelines · Other, Odisha

Proposed Intake Water Pipe Line Corridor for Ttps Expansion Project (2 X 660MW) by NTPC

Proposed Intake Water Pipe Line Corridor for Ttps Expansion Project (2 X 660MW) by NTPC is a rejected pipeline project in Other, Odisha. It seeks 14.9 acres of forest land. Its stated project cost is ₹396.1 crore. As of 27 Nov 2026, its status is “Not approved” (since 21 Sept 2023).

See it on the live map All projects in Other

Data last refreshed 27 Nov 2026, 6:36 am IST. We check for new filings and status changes twice a day.

Project details

Official titleConstruction of the Proposed Intake Water Pipe Line Corridor for Ttps Expansion Project (2 X 660MW)
StatusNot approved
Status since21 Sept 2023
Application filed12 Nov 2022
Approval soughtForest land use
Application typeNew project
SectorPipelines
ApplicantNTPC Limited (NTPC)
Forest land14.9 acres (6 ha)
Project cost₹396.1 crore
DistrictOther
StateOdisha
Location fromSite boundary on record
Our referenceWID-OR-04328

Where it is

Other, Odisha. The exact site boundary, satellite view and the full approval history are on the live map — free with a Google sign-in.

Other projects nearby

All 129 NTPC projects across India

About this information

This page is compiled from publicly available approval records and rewritten in plain language. Statuses can change between our updates, so check with the authority before making decisions. Spotted a mistake? Tell us.